Hợp đồng & Thực hiệnCâu 702 / 1605
A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
a.Acceptable if filled in later that day
b.A prohibited act and grounds for disciplinary action
c.Allowed if the homeowner initials each blank
d.Allowed for repeat customers
Giải thích
B&P §7161 makes it a prohibited act (and cause for discipline) to cause a buyer to sign a contract containing blank spaces to be filled in after signing.
Trích dẫn luật: B&P §7161Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Which document, warning homeowners that unpaid subcontractors and suppliers may place a claim against their home, must be included in a home improvement contract?
- A home improvement contract states the project 'will start sometime soon and finish when done.' What is the defect?
- Which of the following is a mandatory element that must appear in every written home improvement contract?
- After a home improvement contract is signed, when must the contractor give the homeowner a copy?
- A change order that increases the price of a home improvement project by $3,000 is agreed to verbally on-site. To be enforceable under §7159, the change order must be:
- Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)