Which mandatory notice informs the homeowner that they may cancel the transaction within a stated period and how to do so?

a.The Preliminary Notice sent by a subcontractor or supplier
b.The Certificate of Occupancy issued by the building department
c.The Notice of Completion the owner records after the work
d.The 'Notice of the Three-Day Right to Cancel' form

Giải thích

B&P §7159(e) requires the contract to carry, near the buyer's signature, a notice captioned 'Three-Day Right to Cancel' — 'Five-Day' for a senior citizen, seven business days for repairs after a declared disaster — stating the transaction date, the date by which a cancellation must be sent and where to send it, plus a detachable Notice of Cancellation form in duplicate, in the language of the sales presentation. (a) is a lien document: Civil Code §8200 makes preliminary notice a precondition to a lien, a stop payment notice or a payment bond claim, and it can arrive up to 20 days after the claimant starts work. (c) is the owner's recorded notice, which shortens a subcontractor's lien deadline from 90 days after completion to 30 days after recording (Civil Code §8414). (b) is the building department's sign-off that the structure may be occupied.

Trích dẫn luật: Bus. & Prof. Code §7159(e); Civil Code §8200, §8182

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi