Which of the following must a home improvement contract include regarding the work to be done?

a.A description of the project and the significant materials and equipment
b.The total contract price, and nothing further about the work that will be done
c.The contractor's bank account details, so the owner can wire progress payments
d.The completion date alone, with the work described orally at the job site instead

Giải thích

B&P §7159(d)(7) requires the heading 'Description of the Project and Description of the Significant Materials to be Used and Equipment to be Installed', followed by that description. It is what makes the scope enforceable and what any change order has to be measured against. (b) is the bare-price contract the statute exists to outlaw; the price is required too (§7159(d)(5)), but a price with no described scope is not a compliant contract. (d) leaves the scope oral, which is exactly what §7159(d) forbids. (c) is required nowhere and solves nothing: §7159.5(a)(5) bars accepting payment beyond the value in place, so a wire authorization is no substitute for a payment schedule.

Trích dẫn luật: Bus. & Prof. Code §7159(d)(5), (7); §7159.5(a)(5)

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi