Hợp đồng & Thực hiệnCâu 727 / 1605
Which of the following must a home improvement contract include regarding the work to be done?
a.A description of the significant materials to be used and the work to be performed
b.Only the total price
c.The contractor's bank information
d.Just the completion date
Giải thích
B&P §7159 requires the contract to include a description or plan of the work to be done and the materials to be used and equipment to be installed.
Trích dẫn luật: B&P §7159(c)Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A homeowner calls a plumber for an urgent $400 leak repair. The plumber may use a service and repair contract only if, among other conditions, the plumber:
- Failing to give the homeowner a copy of the signed home improvement contract is:
- A contractor pre-prints the contract 'date' as the day AFTER the actual signing to shorten the buyer's cancellation window. This is:
- A valid service and repair contract must still give the buyer:
- On a $50,000 whole-house remodel, a contractor wants the largest lawful down payment. Without a joint control, that amount is:
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)