Hợp đồng & Thực hiệnCâu 732 / 1605
The 'Notice to Owner' that must accompany a home improvement contract primarily explains:
a.The resale value of the home
b.The contractor's insurance policy limits
c.How to obtain a building permit
d.The owner's rights and responsibilities under the mechanics lien laws
Giải thích
The Notice to Owner required with home improvement contracts educates the property owner about the mechanics lien laws and the risk that unpaid subcontractors or suppliers could lien the property.
Trích dẫn luật: B&P §7159(c)Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- On a $50,000 whole-house remodel, a contractor wants the largest lawful down payment. Without a joint control, that amount is:
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
- The three-day right to cancel a home improvement contract applies primarily to contracts that are:
- A contractor's payment schedule requires the owner to pay 80% of the price before any materials arrive or work begins. This violates §7159 because:
- Which scenario would DISQUALIFY a job from using the service and repair contract form?
- The required title 'Home Improvement' and the mandatory notices in a §7159 contract must be presented in a way that is:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)