'Frustration of purpose' as an excuse for nonperformance applies when:

a.An unforeseen event destroys the shared purpose, although performance still remains possible
b.An unforeseen event destroys the subject matter itself, making performance physically impossible
c.An unforeseen event makes performance far costlier than either of the parties had ever expected
d.One party simply finds the bargain a good deal less attractive than it had originally hoped for

Giải thích

Frustration of purpose excuses performance when an event neither party foresaw destroys the principal purpose both understood as the basis of the bargain, even though the promised performance remains entirely possible — the textbook case is renting a room to watch a parade that is then cancelled. (b) is impossibility, where performance itself cannot be rendered; the doctrines are neighbours, not synonyms, and Civil Code §1511 sets out when performance is excused. (c) is commercial impracticability, which California applies narrowly: added cost, even large added cost, is the risk a fixed-price contractor accepted. (d) is buyer's remorse, which excuses nothing at all.

Trích dẫn luật: Civil Code §1511

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi