A contractor's bid includes $30,000 labor, $25,000 materials, $15,000 subs, and a 20% markup on the total direct cost. What is the bid price?
a.$84,000 including $14,000 markup
b.$14,000
c.$70,000
d.$78,000
Giải thích
Direct cost = $30,000 + $25,000 + $15,000 = $70,000. Markup = 20% x $70,000 = $14,000. Bid = $70,000 + $14,000 = $84,000.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A contractor's estimate omitted the 9% sales tax on $20,000 of materials. How much profit will this error erase if he cannot pass it on?
- A contractor's business is organized as an S corporation. A key financial feature of an S corp is that:
- A C corporation differs from a sole proprietorship in that the C corporation:
- A contractor's fixed monthly overhead is $12,000. In a slow month he completes work generating only $9,000 of contribution margin. His result for the month is:
- A quick way to see if a business can pay its short-term bills is to check its:
- A contractor buys a $2,400 laptop, a $600 printer, and $150 of paper. Which is most likely expensed immediately rather than capitalized?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)