Section 1541(i) requires a support system such as shoring, bracing or underpinning in which situation?
Giải thích
Section 1541(i)(1) requires support systems, shoring, bracing or underpinning wherever excavation endangers the stability of adjoining buildings, walls or other structures, and (i)(2) applies it specifically where the excavation goes below the base or footing of a foundation or retaining wall. The other three are real conditions governed by other rules. A spoil pile at four feet already clears the two-foot minimum in (j)(2) and creates no support duty. Previously disturbed soil matters a great deal, but through Appendix A - it forces the material into Type C and flattens the required slope - not through (i). And (i)(3) bars UNDERMINING sidewalks and pavements; one sitting alongside at grade and not undercut is not undermined.
Trích dẫn luật: 8 CCR §1541(i)(1)-(3); §1541(j)(2); §1541.1 Appendix ALuyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- Before entering a trench more than 4 feet deep where a hazardous atmosphere could exist (e.g., near landfill or sewer), the employer must:
- In the excavation soil classification system, which classification is the most stable?
- For a simple sloping system in Type C soil (and no engineering), the maximum allowable slope is approximately:
- Each scaffold and scaffold component must be capable of supporting, without failure, its own weight and at least how many times the maximum intended load?
- At what height above a lower level does fall protection become required for employees on a supported scaffold?
- Who must inspect a scaffold before each work shift and after any occurrence that could affect its structural integrity?
Cập nhật gần nhất: · quy trình kiểm tra