A licensee willfully departs in a material respect from accepted trade standards for good and workmanlike construction. What does the license law provide?
解析
B&P §7109(a) makes a willful material departure from accepted trade standards a cause for disciplinary action, unless the departure followed plans prepared by or under an architect's supervision; §7110 does the same for willful disregard of building, safety, labor, and compensation insurance laws. (a) confuses the forums: a building department can require correction, but only the Registrar can reach the license. (c) makes a civil judgment a precondition the statute does not impose — CSLB discipline runs independently of the owner's contract remedies. (d) mistakes the track: workmanship discipline is administrative, and no conviction is needed for the Registrar to act.
法律依据: B&P Code §7109(a) / §7110免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- A licensee changes the business name style (for example, from 'ABC Builders' to 'ABC Construction Inc.'). What is generally required?
- A sole proprietor licensee incorporates the business. Can the new corporation keep operating under the sole proprietor's license number without action?
- Claims against the $25,000 contractor's license bond are generally handled how when total claims exceed the bond amount?
- A licensee willfully and deliberately disregards state and local building laws. What does §7110 make of that?
- Diversion of funds or property received for a specific construction project, causing inability to complete it, is known as what violation?
- On a private project, a prime contractor must generally pay a subcontractor its share of a progress payment within how many days after receiving that payment from the owner?
最近核对: · 审核流程