企业组织与执照第 1438 / 1632 题

On a private project, a prime contractor must generally pay a subcontractor its share of a progress payment within how many days after receiving that payment from the owner?

a.30 days
b.7 days
c.60 days
d.90 days

解析

Under B&P Code section 7108.5 a prime contractor must pay each subcontractor its share within seven days after receiving a progress payment from the owner (b). Wrongful withholding carries a 2%-per-month penalty plus attorney's fees and is grounds for discipline. (a) 30 days and (d) 90 days are commercial terms, not the statute's. (c) 60 days is the Public Contract Code §7107 window for a public agency to release retention after completion — a different rule for a different project type. The 10-day figure candidates often reach for is Civil Code §8814, which governs passing RETENTION through to a subcontractor, not progress payments.

法律依据: B&P Code §7108.5

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈