保险与留置权第 1529 / 1632 题
A contractor who records a mechanics lien for an amount it knows is willfully overstated risks:
a.Nothing, because the court simply reduces the lien to the correct sum
b.A recording fee penalty only, with the lien enforceable as corrected
c.Losing the entire lien and being liable to the owner for damages
d.Having the lien reduced and the excess added to the payment bond claim
解析
Civil Code §8422 makes a claim of lien void to the extent it includes work not provided or is willfully overstated, and the claimant can lose the lien altogether and face liability for the owner's resulting damages. (a) is the widespread and costly assumption that padding is free because a judge will simply trim it. (b) treats the consequence as a fee. (d) invents a transfer between remedies — overstating a lien does not move the surplus onto a bond, and a willfully false bond claim carries its own exposure.
法律依据: Civil Code §8422免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- On a private project financed by a construction lender, a subcontractor who fails to serve the preliminary notice on the LENDER primarily loses the ability to:
- 'Subrogation' in insurance refers to:
- A waiver of subrogation clause between an owner and a contractor generally means:
- Separate from project insurance, the CSLB requires every active licensed contractor to maintain a 'contractor's bond' (contractor license bond). Its main purpose is to:
- Which statement about the CSLB license bond and a project performance bond is TRUE?
- A preliminary notice must be given by which method to be effective?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)