合同与履行第 717 / 1632 题
A home improvement contract must be written in the same language principally used in the:
a.County where the property is located
b.Local building code
c.Contractor's license application
d.Oral sales presentation or negotiation
解析
B&P §7159 requires that the home improvement contract be written in the same language (for example, Spanish) that was principally used in the oral sales presentation or negotiation.
法律依据: B&P §7159(c)免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- When a homeowner properly exercises the three-day right to cancel a home improvement contract, the contractor must return any down payment within:
- A contractor and homeowner agree on a $9,000 bathroom remodel. The three-day right to cancel period generally begins:
- A contractor includes a clause in the home improvement contract stating the buyer waives their right to cancel. This clause is:
- Under §7159.5, a contractor may NOT do which of the following regarding down payments and progress payments?
- 'Joint control' in the context of a home improvement project refers to:
- When a home improvement contract's funds are handled through an approved joint control, the effect on the standard down payment and progress payment limits is that they:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)