商业财务第 1113 / 1605 题
A contractor's job has $10,000 direct costs. He adds 15% for overhead and then 10% profit on the resulting subtotal. What is the final price?
a.$12,500
b.$11,650
c.$12,650
d.$12,750
解析
Direct cost $10,000 + 15% overhead ($1,500) = $11,500 subtotal. Then 10% profit on $11,500 = $1,150. Final price = $11,500 + $1,150 = $12,650. Order matters: overhead first, then profit on the total.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A contractor applies a 100% markup on a $3,000 cost. What margin does that represent, and what is the price?
- A contractor's annual overhead is $120,000 and he expects $600,000 in direct job costs this year. What overhead rate should he add to each job's direct cost to recover overhead?
- Which of the following is an example of OVERHEAD (indirect cost) rather than a direct job cost?
- Overhead costs are best described as:
- A contractor completes $800,000 in revenue with $560,000 direct costs and $160,000 overhead. What is the net profit and net profit margin?
- If a contractor underestimates his overhead rate when bidding, the most likely result is: