商业财务第 1234 / 1605 题
A contractor's markup covers overhead and profit. If direct costs are $80,000 and he applies a combined 25% O&P markup, the profit portion is $8,000 while overhead recovery is $12,000. What is the contract price and total O&P?
a.Price $100,000; O&P $20,000
b.Price $88,000; O&P $8,000
c.Price $105,000; O&P $25,000
d.Price $100,000; O&P $12,000
解析
Combined O&P markup = 25% x $80,000 = $20,000, split into $12,000 overhead recovery + $8,000 profit as stated. Price = $80,000 + $20,000 = $100,000. Total O&P added is $20,000.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A balance sheet is said to 'balance' because:
- A contractor factors (sells) $50,000 of receivables to a factor who advances 90% now and charges a 3% fee on the face amount. How much cash does the contractor receive up front, and what is the fee?
- A contractor's income statement is prepared monthly, but the balance sheet is dated December 31. This is because:
- A contractor pays estimated federal taxes of $6,000 per quarter. If he skips a quarter to fund payroll and pays it late, the likely consequence is:
- A contractor with a 2.0 current ratio has $160,000 in current liabilities. What are his current assets?
- A contractor mixing personal and business funds in one account risks: