The primary purpose of JOB COSTING is to:
a.Spread the overhead evenly over every job
b.Track real costs against the estimate
c.Determine the sales tax owed on the materials
d.Set an hourly price for the next job to bid
解析
Job costing records the labour, material, subcontract and equipment cost actually incurred on each project and sets it beside the estimate, so the contractor learns which jobs made money and bids the next one better. Spreading overhead is what the overhead rate does, and it is an input to the bid rather than the purpose of job costing. Sales tax is computed from purchase invoices. And an hourly price for the next job is guesswork unless the job history behind it has been costed.
免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- If a contractor's fixed costs rise while his contribution margin ratio stays the same, the break-even point will:
- A framing job needs 3,200 board feet of lumber at $0.85 per board foot, plus 40 labor hours at $45/hour. What is the estimated direct cost?
- A contractor estimates a job at 120 labor hours. Actual hours worked were 150. By what percentage did labor hours exceed the estimate?
- A concrete slab is 30 ft x 40 ft x 4 inches thick. How many cubic yards of concrete are needed? (1 cubic yard = 27 cubic feet)
- A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
- A painting job covers 2,400 square feet. One gallon covers 350 sq ft. How many gallons (rounded up to full cans) are needed for two coats?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)