安全第 1259 / 1605 题
Who must inspect an excavation for hazardous conditions before employees enter and as conditions change?
a.Any available laborer
b.The equipment rental company
c.The project architect
d.A competent person
解析
A 'competent person' must conduct daily inspections of excavations before each shift and as needed. A competent person can identify hazards and has authority to take prompt corrective action.
法律依据: 29 CFR 1926.651(k) / T8 CCR §1541免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A guardrail system used for fall protection must have a top rail capable of withstanding a downward/outward force of at least how much, applied within 2 inches of the top edge?
- The top edge of a standard guardrail top rail must be approximately what height above the walking/working surface?
- At what depth does an excavation generally require a protective system such as sloping, shoring, or shielding to protect workers from cave-ins?
- For an excavation deeper than 20 feet, protective systems (such as shoring or shielding) must be:
- A trench is 5 feet deep. What means of egress must be provided for workers?
- Excavated spoil, materials, and equipment must be kept at least how far back from the edge of an excavation?