Excavated spoil, materials, and equipment must be kept at least how far back from the edge of an excavation?

a.6 inches
b.1 foot
c.4 feet
d.2 feet

解析

Section 1541(j)(2) requires excavated material and equipment to be kept at least 2 feet from the edge, or to be held by retaining devices sufficient to stop it falling or rolling in, or both. The setback is doing two jobs at once, which is why the standard offers the alternative: the spoil can roll in on a worker, and its weight is a surcharge load that helps cause the cave-in in the first place. Six inches and one foot are too close to do either. Four feet is more than the standard asks and is the figure a candidate reaches for by confusing the setback with a sloping offset.

法律依据: 8 CCR §1541(j)(2); 29 CFR 1926.651(j)(2)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈