Why is setting a slope stake usually a trial-and-error process in the field?

  • a.The centerline elevation changes while the stake is in the process of being set
  • b.The slope ratio of the cut or fill is not known until the grading has started
  • c.The catch point distance depends on the ground elevation at the catch point itself✓
  • d.The offset to the hinge point varies with the weather conditions on the day

The distance out equals the hinge offset plus the slope ratio times the height difference, but that height depends on the ground elevation where the rod stands. The surveyor tries a position, compares measured and computed distances, and moves until they agree.

Construction Surveying

On a stationed alignment, what does station 12+50 mean?

  • a.A point 12.50 ft along the alignment from station 0+00
  • b.A point 12 ft right and 50 ft ahead of station 0+00
  • c.A point 1,250 ft along the alignment from station 0+00✓
  • d.A point 1,250 ft at right angles to the alignment

Stationing counts distance along the alignment in 100-ft stations plus feet: 12+50 is 12 full stations and 50 ft, or 1,250 ft. Distances at right angles to the alignment are offsets, stated left or right when facing up-station.

Construction Surveying

What is a grade break in construction staking?

  • a.A point where the contractor's work stops at the end of a shift
  • b.A point where the staking offset distance changes for clearance
  • c.A point where the existing ground matches the design elevation
  • d.A point where the design slope of the surface or line changes✓

Stakes are needed at grade breaks because the contractor builds straight grades between stakes; missing one produces a surface that cuts across the designed change in slope. A point where existing and design grades coincide is a daylight or no-cut, no-fill point.

Construction Surveying

When staking a gravity sewer, which elevation is normally referenced on the stake?

  • a.The top-of-pipe (crown) elevation
  • b.The trench bedding elevation
  • c.The finished pavement elevation
  • d.The pipe invert (flow line) elevation✓

Gravity pipes are designed and built to invert grade, since the flow line controls hydraulic performance. Cuts are therefore given to invert, and the contractor allows for pipe wall thickness and bedding. Using the crown instead misplaces the pipe by its diameter.

Construction Surveying

Before staking from a set of plans, the engineer's crew checks into two control points and finds a 0.4-ft discrepancy. What should be done?

  • a.Stake from the nearer control point and ignore the other entirely
  • b.Split the difference equally among all of the stakes set that day
  • c.Resolve the control discrepancy before setting any construction stakes✓
  • d.Proceed with staking and note the discrepancy on the cut sheet

Staking from bad control transfers the error into the built work. The cause must be found first: a disturbed point, a wrong coordinate, a datum mix-up or a grid-to-ground mistake. Splitting or ignoring a 0.4-ft discrepancy hides a problem that may be much larger elsewhere.

Construction Surveying

What is the purpose of a cut sheet (grade sheet) given to the contractor?

  • a.To list each stake with its station, offset, hub elevation, design grade and cut or fill✓
  • b.To record the quantities of excavation that have been completed for a progress payment
  • c.To show the property boundary and the easements that cross the limits of the work
  • d.To certify that the completed work has been inspected and accepted by the agency

The cut sheet documents what was staked and lets the contractor and inspector verify each cut or fill arithmetically (hub elevation minus design grade). It is neither a payment record nor a boundary map, and it carries no acceptance of the work.

Construction Surveying

A building is laid out with batter boards. What is their function?

  • a.To mark the finished floor elevation on the inside of the walls
  • b.To hold string lines on the building lines clear of the excavation✓
  • c.To support the sides of the footing trench until it is concreted
  • d.To protect the survey control points from construction traffic

Batter boards are set outside the excavation; strings stretched between them reproduce the building lines and often a reference elevation after corner stakes are dug out. Trench support is shoring, a different thing altogether.

Construction Surveying

What does the term 'daylight line' describe on a grading plan?

  • a.The line where the proposed slope meets and matches existing ground✓
  • b.The line of the crown along the center of the proposed pavement
  • c.The line of the property boundary along the edge of the grading
  • d.The line of the hinge points along each of the two shoulders

Daylight is where a designed cut or fill slope intersects natural ground, the line of catch points. Outside it the ground is undisturbed. Its position relative to property lines and easements is a common design check, but it is not itself a boundary.

Construction Surveying

During curb staking on a horizontal curve, why are stakes set at closer intervals than on tangent?

  • a.The offset distance must be changed at every stake along a curve
  • b.Curved curb is given a steeper longitudinal grade than tangent curb
  • c.Short chords between stakes follow the arc closely enough to build from✓
  • d.The deflection angle cannot be computed for arcs longer than 25 ft

The contractor strings a straight line between stakes. The gap between chord and arc grows with the square of the chord length, so short spacing on tight radii keeps the built curb on the designed arc. Grade and offset conventions do not change on a curve.

Construction Surveying

After construction, a surveyed pipe invert is found 0.30 ft higher than the plan elevation at the downstream manhole. What is the appropriate use of that information?

  • a.Report it on the as-built record so that the effect on slope can be evaluated✓
  • b.Disregard it, because inverts are accepted within one foot of the plan
  • c.Adjust the upstream benchmark by 0.30 ft so that the invert agrees
  • d.Change the plan elevation so that the record matches what was constructed

As-built data exists to show what was actually constructed; a higher downstream invert flattens the pipe and may affect capacity, which is an engineering question. Altering the design record or the benchmark to hide the difference misrepresents the work.