Planning
Planning is the step between findings and work. The field representative turns what was found into recommendations that meet regulation 1991, chooses methods the company is registered to use, calculates quantities from the label and prepares the notices the customer must receive.
Recommendations the regulation requires
Regulation 1991 sets the standard recommendations for a complete report. Excessive cellulose debris in earth contact is removed. Faulty grades, earth-filled planters and loose stucco are corrected where they have led to moisture or infestation. Structurally weakened members are replaced or reinforced. All reported wood-destroying pests are exterminated. Accessible pellets and frass are removed or covered. Commonly controllable excessive moisture is corrected. Where there is reasonable evidence of fungus in a concealed wall, the wall is opened.
Whole-structure or local treatment
Where evidence shows an infestation extends into inaccessible areas, the recommendation is fumigation, another all-encompassing method, or local treatment. Any recommendation for local treatment must carry the statement that local treatment is not intended to be an entire structure treatment method. Fumigation and whole-structure heat reach insects in wood throughout the building; neither affects a subterranean colony in the soil, and fumigation leaves no residue.
Subterranean termites
Where tubes connect to the ground, the infested area under the structure is treated and accessible tubes are removed. Tubes may stay only while an above-ground bait station that depends on them is in use, and are removed when that treatment ends. A bait station requires a full or limited inspection first and is handled as a control service agreement.
Secondary recommendations and subcontracting
Regulation 1992 allows a report to offer a lesser measure as a secondary recommendation, provided it is labelled as such, fully explained and noted as below standard. Later documents must say which work was secondary. Section 8514 lets a Branch 3 company recommend a method outside its registration, such as fumigation, if it subcontracts the work in writing to a company registered for it; fumigation may be subcontracted only with the consumer's written consent.
Quantities and precautions
Soil termiticide labels state volume per 10 linear feet per foot of depth for trenching and rodding, and per 10 square feet for horizontal treatment. Divide the length or area by ten and multiply by the rate, then by the depth where it applies. Pre-construction applications are never made at less than the label rate. Before a soil treatment, locate wells, cisterns, drains, heating ducts and utilities, and follow the label's restrictions for each.
How this area is tested
Questions give a finding and ask for the recommendation, or give a label rate and ask for gallons. Calculators are not allowed, so practise the arithmetic by hand. When a question offers a cheaper shortcut, remember that the standard recommendation must always appear in the report; anything less is secondary and labelled so.
Keep going: the full California Structural Pest Control Field Representative — Branch 3 (Termite) guide covers every section of the exam. Branch 3 Field Representative Exam — California Termite Study Guide, 2027 Edition — PDF + EPUB, $14.99 · 14-day refund →

Practice stays free. The full California Structural Pest Control Field Representative — Branch 3 (Termite) study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.