Drywood termite evidence extends into wall voids that cannot be reached. Which recommendation meets the regulation?

  • a.A surface spray of the exposed framing in the attic
  • b.An all-encompassing treatment such as fumigation✓
  • c.Removal of the pellets only
  • d.A reinspection in four months

Section 1991 says that when evidence indicates wood-destroying pests extend into inaccessible areas, the recommendation is fumigation, another all-encompassing method, or local treatment by exposing or removing the infested wood.

Planning

Which statement must accompany any recommendation for local treatment?

  • a.Local treatment replaces all future inspections of the whole structure
  • b.Local treatment is required by the building code in every California city
  • c.Local treatment is not intended to be an entire structure treatment✓
  • d.Local treatment is guaranteed for as long as the building stands

Section 1991 prescribes wording warning that infestations beyond the treated area may not be exterminated.

Planning

What does "all-encompassing treatment" mean in the regulation?

  • a.A method that treats only the accessible attic and subarea timbers
  • b.A soil treatment around the whole foundation
  • c.A method that treats the whole structure, such as fumigation✓
  • d.A coat of paint on exposed wood

The regulation refers to enclosing the structure for treatment with a fumigant, or another method that exterminates the infestation of the structure.

Planning

May a Branch 3 company recommend and contract for fumigation?

  • a.Yes, if it subcontracts the work in writing to a Branch 1 company✓
  • b.Yes, and it may fumigate itself under its Branch 3 registration
  • c.No, it may not mention fumigation in its report
  • d.Yes, but only for subterranean termites

Section 8514 lets a company recommend a method outside its branch if it subcontracts performance in writing to a company registered for that method.

Planning

What must the consumer give before fumigation work is subcontracted?

  • a.Oral consent
  • b.Written consent✓
  • c.A deposit of half the price
  • d.Nothing in writing at all

Section 8514(e) bars subcontracting structural fumigation without the consumer's written consent, after written advance notice of the right to choose another company.

Planning

Subterranean termite tubes are found connected to the ground under a house. What is recommended?

  • a.Paint the foundation with sealer
  • b.Treat the infested area and remove the accessible tubes✓
  • c.Fumigate and leave the tubes in place as a monitor
  • d.Leave the tubes as a monitor of activity

Section 1991 calls for treating the infested area under the structure and removing tubes where accessible, unless an above-ground bait station needs them.

Planning

When may subterranean termite tubes be left in place?

  • a.While an above-ground bait station that needs them is in use✓
  • b.Whenever the owner prefers to keep them
  • c.When they are short and no live termites are seen
  • d.When the soil is dry and no rain is forecast

Tubes may remain for the duration of above-ground baiting that depends on them, and must be removed at the conclusion of the treatment.

Planning

Why is fumigation not recommended for subterranean termites alone?

  • a.Subterranean termites are not wood-destroying pests at all
  • b.The label forbids use on softwood framing
  • c.Fumigants do not kill termites, whatever the species or caste
  • d.The colony is in the soil, outside the fumigated space✓

Fumigants leave no residue and do not reach the soil colony, which would simply reinfest. Soil treatment or baiting addresses the source.

Planning

Which pest is best suited to control by whole-structure fumigation?

  • a.Wood-decay fungus spreading in a wet bathroom subfloor
  • b.Drywood termites spread through inaccessible framing✓
  • c.Carpenter ants nesting in a tree
  • d.Subterranean termites entering through a crack in the slab

Fumigation reaches insects inside wood throughout the building. It does nothing for soil colonies or fungus, whose causes must be corrected.

Planning

What must a complete inspection report recommend about drywood pellets and beetle frass?

  • a.Send samples of them to the Board for analysis
  • b.Remove or cover all that are accessible✓
  • c.Leave them in place as evidence for the next inspector
  • d.Spray them with insecticide and leave them

Section 1991 requires a recommendation to remove or cover accessible pellets and frass, so that new evidence can be told from old.

Want these explained in order? Branch 3 Field Representative Exam — California Termite Study Guide, 2027 Edition — PDF + EPUB, $14.99 · 14-day refund →

Planning

What is recommended for cellulose debris in the subarea?

  • a.Burial of the debris well under the subarea soil
  • b.Removal of all excessive debris in earth contact✓
  • c.Treatment of the debris in place with termiticide
  • d.No action if it is dry

The regulation calls for removal. Only stumps and wood embedded in footings may be treated when removal is impractical.

Planning

A tree stump lies partly under a footing and cannot be removed. What may be recommended?

  • a.Raising the house
  • b.Fumigation of the house
  • c.No action
  • d.Treatment of the stump✓

Section 1991 allows stumps and wood embedded in footings in earth contact to be treated if removal is impractical.

Planning

A fungus infection is believed to exist inside a closed wall. What is recommended?

  • a.Opening the wall or area✓
  • b.Waiting until damage shows
  • c.Painting the wall
  • d.Fumigation

Where there is reasonable evidence of fungus in a concealed wall or area, section 1991 requires a recommendation to open it.

Planning

Which recommendation deals with a fungus infection at its cause?

  • a.Install bait stations around the house
  • b.Fumigate the structure with a gas
  • c.Correct the moisture condition✓
  • d.Apply insecticide to the soil below

Fungi cannot grow in dry wood. Section 1991 requires correction of any commonly controllable excessive moisture condition.

Planning

What is a secondary recommendation?

  • a.A lesser measure, labelled as below standard✓
  • b.A recommendation made by a second company
  • c.A second copy of the primary recommendation
  • d.A recommendation for work in Section II only

Section 1992 lets a report suggest secondary recommendations if they are labelled, fully explained and noted as below standard measures.

Planning

If secondary recommendations are carried out, what must later documents say?

  • a.That the work meets every standard
  • b.That the Board inspected and approved the work
  • c.Which work was secondary and substandard✓
  • d.Nothing beyond the price

Any completion letter, billing or other document must state specifically which recommendations were secondary and substandard.

Planning

A customer asks for a bid on each recommendation. What must the company provide?

  • a.A bid for the Section I items only, not Section II
  • b.The cost of each recommendation, separately✓
  • c.A single bid given after the work has been finished
  • d.One lump-sum total for all the work, never itemised

Section 8516 requires an estimate separately allocating costs for each recommendation if requested and if the company regularly performs each corrective measure.

Planning

Which item must the report recommend when a faulty grade has let moisture or infestation develop?

  • a.Fumigation
  • b.Correction of the condition✓
  • c.Removal of the siding
  • d.Nothing, since grade is a Section II item

Section 1991 calls for a recommendation to correct faulty grades, earth fill planters or loose stucco where they have led to moisture, infestation or infection.

Planning

Which is a non-chemical whole-structure method for drywood termites?

  • a.Foam injection
  • b.Soil rodding
  • c.Borate spray
  • d.Heat treatment✓

Heating the structure so that wood reaches a lethal temperature treats the whole building without a fumigant. The other methods are local or soil treatments.

Planning

Which factor most favours local treatment over fumigation for drywood termites?

  • a.The evidence extends into inaccessible voids
  • b.The infestation is confined to accessible members✓
  • c.The infestation is in every room
  • d.The owner wants a certification for the whole building

Local treatment suits a limited, reachable infestation. Wider or hidden infestations call for an all-encompassing method.

Want these explained in order? Branch 3 Field Representative Exam — California Termite Study Guide, 2027 Edition — PDF + EPUB, $14.99 · 14-day refund →

Planning

What must be given to occupants before a Branch 3 pesticide application?

  • a.A building permit for the treatment, signed by the owner
  • b.A lien release from each of the company's suppliers
  • c.The written notice required by section 8538✓
  • d.A copy of the company's registration and licence

The notice names the pest, the pesticide and active ingredients, and carries the caution statement and contact information.

Planning

When planning a soil treatment, what must be located first?

  • a.The property's tax records and assessed value
  • b.Wells, drains, ducts and utilities✓
  • c.The nearest hardware shop
  • d.The neighbours' fences

Termiticide must not reach water supplies or heating ducts, and drilling must avoid pipes and wiring. Labels carry specific restrictions.

Planning

A heating duct runs within the slab to be treated. What does the plan require?

  • a.Following the label's precautions for ducts in or under slabs✓
  • b.No special step of any kind is needed
  • c.Injecting directly into the duct to spread the dilution
  • d.Raising the application rate near the duct

Termiticide entering ducts can be blown into living space. Labels restrict or set special procedures for such construction.

Planning

How is the amount of termiticide for a trench calculated?

  • a.From the number of termites seen
  • b.From the price of the product
  • c.From the label rate per linear feet and depth✓
  • d.From the size of the house in square feet

Soil termiticide labels give gallons per 10 linear feet per foot of depth for trenching and rodding.

Planning

A label calls for 4 gallons per 10 linear feet per foot of depth. How much is needed for 120 linear feet, one foot deep?

  • a.480 gallons
  • b.12 gallons
  • c.40 gallons
  • d.48 gallons✓

One hundred and twenty feet is twelve units of 10 feet. Twelve times 4 gallons is 48 gallons.

Planning

A label calls for 4 gallons per 10 linear feet per foot of depth. How much is needed for 50 linear feet with a footing two feet deep?

  • a.40 gallons✓
  • b.100 gallons
  • c.8 gallons
  • d.20 gallons

Fifty feet is five units; five times 4 gallons is 20 gallons per foot of depth, and two feet of depth doubles it to 40.

Planning

A slab label rate is 1 gallon per 10 square feet. How much is needed for a 20 by 30 foot slab?

  • a.600 gallons
  • b.50 gallons
  • c.60 gallons✓
  • d.6 gallons

The area is 600 square feet, which is 60 units of 10 square feet, so 60 gallons.

Planning

A termiticide is mixed at 0.8 gallon of concentrate per 100 gallons of water. How much concentrate goes into 50 gallons?

  • a.4 gallons
  • b.0.4 gallon✓
  • c.0.8 gallon
  • d.1.6 gallons

Half the volume takes half the concentrate: 0.8 divided by 2 is 0.4 gallon.

Planning

At what rate must a pre-construction soil treatment be applied?

  • a.At half the label rate, to protect workers
  • b.At double the label rate
  • c.At any rate the builder accepts
  • d.Not less than the label specifies✓

Section 1991(b) states that pre-construction termiticide application shall not be made at less than the manufacturer's label specifications.

Planning

Which document must a Branch 3 company give when contracting for work that could lead to a lien?

  • a.The inspection tag
  • b.The certification
  • c.The Notice to Owner✓
  • d.The Branch 1 fumigation log

Section 8513 and regulation 1937.16 require Branch 1 and Branch 3 companies to give the prescribed Notice to Owner about mechanics liens.

Planning

Who may be hired to replace structural timbers identified in an inspection report?

  • a.Only a registered Branch 1 fumigation company
  • b.Anyone the neighbour suggests, licensed or not
  • c.A licensed contractor, as section 8556 allows✓
  • d.Only the company that made the original inspection

Section 8556 lets licensed contractors remove and replace wood damaged by pests where the work is identified in an inspection report.

Planning

Which is the main consideration in choosing between liquid soil treatment and baiting?

  • a.The age of the owner
  • b.Site conditions, such as wells or inaccessible soil✓
  • c.The make and model of the company's service vehicle
  • d.The colour of the house and its trim

Baiting suits sites where liquid cannot be applied safely or completely. Both require an inspection and a contract first.

Planning

Under the regulations, how is the use of a termite bait station treated?

  • a.As a secondary recommendation
  • b.As a structural repair
  • c.As a fumigation under Branch 1
  • d.As a control service agreement✓

Section 1993.2 states that use of a termite bait station is considered a control service agreement under section 8516.

Planning

What should the plan for an anobiid infestation in a damp subarea include?

  • a.Removal of the roof covering
  • b.Improved ventilation or moisture control, with treatment✓
  • c.Nothing but monitoring traps for a full year
  • d.Treatment of the attic timbers only, not the subarea

Anobiids depend on moist wood. Drying the subarea makes the wood unsuitable and supports any chemical treatment.

Planning

Why are borates unsuitable for wood exposed to rain or soil?

  • a.They dissolve in water and leach out✓
  • b.They attract termites to the wood
  • c.They are fumigants that escape as gas
  • d.They turn wood black in direct sunlight

Borates are water-soluble salts that diffuse into wood but wash out of unprotected exterior timber.

Planning

What should the inspector recommend for a lyctid infestation confined to a new oak floor?

  • a.Local treatment or replacement of the affected boards✓
  • b.Removal of all subarea debris
  • c.Soil treatment around the whole foundation and under the slab
  • d.Shower testing in each bathroom

The infestation came in with the flooring and is limited to it. Soil work and debris removal address subterranean termites.

Planning

Which surface must be bare for a borate treatment to work?

  • a.The roof above
  • b.The concrete footing below the sill
  • c.The soil beneath it
  • d.The wood being treated✓

Paint, varnish and sealers block penetration, so borate solutions are applied to unfinished wood.

Planning

What is an essential planning step before recommending heat treatment?

  • a.Identifying heat-sensitive contents and hard-to-heat areas✓
  • b.Locating the water meter and the gas shut-off valve
  • c.Testing the shower pan in each bathroom
  • d.Measuring the grade around the house

Items such as plastics and electronics can be damaged, and large timbers or areas against slabs heat slowly and need monitoring.

Planning

Evidence of old, inactive drywood infestation is found and has been treated before. What does good practice require?

  • a.Recommend fumigation in every case of old evidence
  • b.Leave it off the report as inactive
  • c.Report the evidence and what was observed about activity✓
  • d.Call it an active infestation in every case

The report describes evidence found. Recommendations follow from what the inspector can determine, and concealing evidence is never acceptable.

Planning

Why must the active ingredient be considered when a site is near water?

  • a.Water makes all pesticides harmless once they are diluted
  • b.Fish are attracted to termiticide that soaks into the soil
  • c.Many termiticides are highly toxic to aquatic life✓
  • d.Nearby water raises the label rate that must be applied

Labels restrict application near wells, cisterns and surface water. The environmental hazards section governs the plan.

Planning

Who decides which corrective method is used at a property?

  • a.The inspector alone, whose choice binds the owner
  • b.The owner, after receiving the report and recommendations✓
  • c.The county agricultural commissioner's office
  • d.The Board, on appeal by the lender

The company recommends; the owner or agent contracts for the work they choose and may seek a second opinion.

Planning

What must exist before any Branch 3 work begins on a contract?

  • a.A completed inspection and a delivered report✓
  • b.A guarantee
  • c.A building permit in every case, whatever the work
  • d.A paid invoice for the full price

Sections 8514 and 8516 bar commencing work until the inspection has been made, and the report must be delivered before work starts.

Planning

What should a field representative do when a recommended repair is beyond the company's trade?

  • a.Leave it out of the report altogether
  • b.Recommend it and let the owner engage a licensed contractor✓
  • c.Describe it as optional work for later
  • d.Do the work anyway, without a contractor's licence

Findings and recommendations must be reported whether or not the company will do the work.

Planning

The label of a wood treatment lists drywood termites but not beetles. May it be used for beetles?

  • a.No; the pest and site must be on the label✓
  • b.Yes, if the owner agrees in writing
  • c.Yes, at double the label rate for drywood termites
  • d.Yes, but only indoors

Use against an unlisted pest or site conflicts with the labelling. The field representative selects a product registered for the job.

Planning

Which treatment plan is appropriate for wood wasps emerging from new framing?

  • a.Fumigation of the whole structure before it is occupied
  • b.Soil treatment
  • c.No treatment; explain that they do not reinfest✓
  • d.Removal of all the framing

Horntails cannot reinfest seasoned wood, so chemical treatment is unnecessary.

Planning

What should the field representative recommend where sprinklers wet the siding daily?

  • a.Apply termiticide to the siding each month
  • b.Redirect or adjust the irrigation✓
  • c.Fumigate the wall
  • d.Install bait stations inside the house

This is a controllable moisture condition. Correcting it removes the cause of decay.

Planning

Which information does a field representative need to estimate a local injection treatment?

  • a.The owner's occupation
  • b.The number and extent of infested members✓
  • c.The height and length of the fence
  • d.The square footage of the lot and the garden

Local treatment is priced and planned by the timbers involved and their accessibility.

Planning

A customer asks only for the cheapest option. What must the report still contain?

  • a.The standard recommendations required by section 1991✓
  • b.Only the cheaper secondary recommendation
  • c.The competitor's prices for the same work
  • d.No recommendations, only the findings

Secondary measures are in addition to the required recommendations, never a substitute.

Planning

What is the purpose of a vapour barrier over subarea soil?

  • a.To reduce moisture rising into the subarea✓
  • b.To replace the foundation vents in the subarea entirely
  • c.To kill subterranean termites in the soil beneath it
  • d.To support the floor joists and girders from below

A ground cover lowers humidity and wood moisture. It is a moisture-control measure, not a pesticide.

Planning

When more than one company bids on the same report, what should be the same in each company's report?

  • a.The prices
  • b.The findings✓
  • c.The guarantee
  • d.The recommendations

The statutory notice explains that findings should match between companies while recommendations may differ.