CAPM (Certified Associate in Project Management) Practice Exam — All Questions

2 questions

Roles & Process Groups

Which list correctly names the five process groups used to organize project management processes?

  • a.Concept, development, delivery, support, and retirement
  • b.Analyze, design, build, test, and deploy
  • c.Initiating, planning, executing, monitoring and controlling, and closing✓
  • d.Define, measure, analyze, improve, and control

The five process groups are Initiating, Planning, Executing, Monitoring and Controlling, and Closing. They are not sequential project phases; several can be active at once and they interact across the project.

Roles & Process Groups

What is the primary role of a project sponsor?

  • a.To perform the technical work of building the deliverables
  • b.To write and maintain every detailed requirement document
  • c.To provide resources and support, champion the project, and remove high-level obstacles✓
  • d.To manage the day-to-day work and schedule of the project team

The sponsor is typically an executive who provides financial resources, authorizes the charter, champions the project, and helps clear organizational obstacles. Day-to-day management is the project manager's responsibility.

Report