Which list correctly names the five process groups used to organize project management processes?
- a.Analyze, design, build, test, and deploy
- b.Initiating, planning, executing, monitoring and controlling, and closing✓
- c.Define, measure, analyze, improve, and control
- d.Concept, development, delivery, support, and retirement
The five process groups are Initiating, Planning, Executing, Monitoring and Controlling, and Closing. They are not sequential project phases; several can be active at once and they interact across the project.
Roles & Process Groups
What is the primary role of a project sponsor?
- a.To manage the day-to-day work and schedule of the project team
- b.To write and maintain every detailed requirement document
- c.To perform the technical work of building the deliverables
- d.To provide resources and support, champion the project, and remove high-level obstacles✓
The sponsor is typically an executive who provides financial resources, authorizes the charter, champions the project, and helps clear organizational obstacles. Day-to-day management is the project manager's responsibility.