4 questions

Tools and Documentation

Which document defines the specific deliverables, activities, and timelines a vendor is contracted to provide?

  • a.Statement of work (SOW)✓
  • b.Risk register
  • c.Organizational chart
  • d.Meeting minutes

A statement of work (SOW) details the deliverables, activities, and timelines expected from a vendor and becomes part of the contract. Meeting minutes record discussions, a risk register tracks risks, and an organizational chart shows reporting structure.

Tools and Documentation

A project manager needs a visual schedule that shows tasks as horizontal bars along a timeline, including their durations and dependencies. Which tool is best?

  • a.A business case
  • b.A stakeholder register
  • c.A Gantt chart✓
  • d.A pie chart of the budget

A Gantt chart displays tasks as horizontal bars along a timeline, showing durations, start and end dates, and dependencies, which makes it ideal for visualizing and tracking a schedule. The other options serve budgeting, stakeholder, or justification purposes.

Tools and Documentation

An organization wants to solicit detailed pricing and solution proposals from multiple vendors for a defined project. Which procurement document should it issue?

  • a.A project charter
  • b.A lessons-learned report
  • c.A meeting agenda
  • d.A request for proposal (RFP)✓

A request for proposal (RFP) asks vendors to propose complete solutions along with pricing for a defined need, allowing comparison of approaches. An RFQ focuses narrowly on price and an RFI gathers general information, while the other documents are internal and unrelated to soliciting bids.

Tools and Documentation

What is the primary purpose of maintaining an issue log during a project?

  • a.To store the project's source code
  • b.To calculate employee payroll
  • c.To track identified problems, their owners, and resolution status✓
  • d.To replace the project charter

An issue log records problems that have already occurred, assigns an owner, and tracks status through resolution so nothing is lost. It differs from a risk register, which tracks potential future events, and it is not a code repository or payroll tool.