CSLB C-21 Building Moving and Demolition (Trade Exam) — Study Guide

Free, topic-by-topic study notes for the CSLB C-21 Building Moving and Demolition (Trade Exam) exam. Read a chapter, then practice it.

FREE SAMPLE — READ IT RIGHT HERE
Chapter 1 · ≈11 min read
Planning and Estimating (25%)
scroll ↓

The Board gives Planning and Estimating about 25% of the C-21 examination, the largest single section, and lists five knowledge statements under it: evaluating plans and specifications, evaluating hazardous materials surveys, evaluating job site readiness, determining job methods and equipment, and estimating project costs.[1] Everything later in this book (permits, mobilizing, moving, demolishing, safety) is a decision you make here first, on paper, before a crew or a machine arrives.

Each unit below has the same parts: what the Board's statement asks of you, numbered rules to carry in your head, at least one worked example done step by step, and the traps that the exam writers like. The exam is closed book, so the rules and numbers are collected again in the key-numbers table at the end of the chapter.

1.1 Evaluating plans and specifications

What a C-21 contractor is licensed to do

Start with the license, because scope questions are planning questions. The Board's classification text says a building moving/demolition contractor "raises, lowers, cribs, underpins, demolishes and moves or removes structures, including their foundations."[2] Read that as a list of verbs: raise, lower, crib, underpin, demolish, move, remove. Each verb is something you may do to a structure, and the foundation goes with the structure.

The sentence that limits the license comes next: the classification "does not include the alterations, additions, repairs or rehabilitation of the permanently retained portions of such structures."[2] That is the edge. If the drawings show a wing coming down and the other wing staying, the removal is C-21 work, but the new framing, the patched exterior wall on the retained side and the rebuilt roof tie-in belong to whoever holds the classification for that work. A C-21 estimate prices the taking-away and the support needed to do it safely; it does not quietly absorb the rebuild.

The documents, and what each one tells you

A set of documents for a moving or demolition job has more parts than a typical building set. Learn what each one is for:

  1. Contract and general conditions. Who owns the debris, who pays for permits, whether salvage belongs to the owner, liquidated damages, work hours.
  2. Drawings. The site plan (property lines, adjacent structures, utilities, access), the existing-conditions plan, the demolition plan (what comes out, what stays, the limit-of-work line) and, for a move, the route plan and the receiving-site foundation plan.
  3. Specifications. Methods and sequence restrictions, dust and noise limits, recycling requirements, protection of items to remain, disposal rules.
  4. Surveys and reports. The structural survey, the hazardous materials survey (Unit 1.2) and any geotechnical report.
  5. Permit conditions. Anything the building official, the air district or the utility added when the permit was issued.

A good habit is to read the legend and the notes before the drawing. Demolition sheets use line types and abbreviations for "remove", "existing to remain", "protect in place" and "salvage". Misreading a dashed line is how a retained wall comes down.

The code anchors for the paperwork

Four rules tell you what has to be in writing before work starts.

  • The Building Code requires a permit for anyone who intends to "construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure." Moving and demolishing are named.[3]
  • Chapter 33 says "Construction documents and a schedule for demolition shall be submitted where required by the building official."[4]
  • Cal/OSHA requires that "a qualified person shall make a survey of the structure to determine the condition of the framing, floors, and walls," that the survey be "in written form, kept on the job-site and made available to the Division upon request," and that adjacent structures where employees may be exposed be checked too.[5]
  • Federal OSHA says the same in other words: an engineering survey "by a competent person," with written evidence that it was done.[6]

Rule 1.1-1 — The two surveys are different documents

The structural survey answers "will this thing fall down while we take it apart?" and is a Cal/OSHA requirement. The hazardous materials survey answers "what is in it that can hurt people or the environment?" and is a different requirement with different authors. A plan review that finds one and assumes the other is complete has found half the problem.

Rule 1.1-2 — Height decides the Cal/OSHA permit

Cal/OSHA requires a permit before demolishing or dismantling "any building or structure more than 36 feet in height." The Project Administrator (the party with overall onsite responsibility, such as the general contractor or owner-builder) holds a Project Permit, and "all other employers directly engaging in demolition or dismantling activity shall hold an Annual Permit."[7] The permit-required list in the same section also includes trenches or excavations "5 feet or deeper into which any person is required to descend."[7] Read the height off the elevation drawings, not off the number of stories.

Worked example 1.1a — Does this job need the Cal/OSHA demolition permit?

A two-story building is shown on the existing-conditions elevation with these dimensions: grade to first floor 2 ft, first floor to second floor 10 ft, second floor to eave 9 ft, eave to ridge 7 ft.

  1. Ask what "height" means for the structure: the Board's rule says "more than 36 feet in height," so measure the whole structure from grade to its highest point.
  2. Add: 2 + 10 + 9 + 7 = 28 ft.
  3. Compare: 28 ft is not more than 36 ft, so the 36-foot demolition permit trigger is not met on height. A trench or excavation 5 feet deep or more that a person descends into, such as a basement foundation being removed by hand, would be a separate permit trigger.[7]

If the same building had a 12-ft parapet and a 20-ft tower, the tower alone would make the structure taller than 36 feet and the permit would be required.

Worked example 1.1b — What the plans must tell you before you bid a partial demolition

A drawing set shows the north wing marked "remove" and the south wing marked "existing to remain". Ask these in order:

  1. Where exactly is the limit-of-work line, and is it a structural line (a bearing wall) or a drawn line?
  2. Is the retained wing sharing a foundation, a roof or a wall with the part coming down?
  3. Who rebuilds the exposed edge: you, or another contractor?
  4. Is there a hazardous materials survey that covers the whole wing, including the shared wall?

If the answer to question 3 is "you", check that you hold the classification for that work; the C-21 definition excludes repairs to the permanently retained portions.[2]

Named traps — plans and specifications

  • "The permit is the contractor's job, so the survey is not." The written structural survey is required before employees start demolition, whoever pulled the permit.[5]
  • Counting stories instead of feet. The Cal/OSHA permit trigger is a height in feet.[7]
  • Assuming the license covers the rebuild. It does not cover alterations or repairs to the portions that stay.[2]
  • Surveying only your own building. Adjacent structures where employees may be exposed must be checked as well.[5]

1.2 Evaluating hazardous materials surveys

What "evaluate" means

The Board says "evaluating hazardous materials surveys." You are not asked to write the survey; you are asked to read it critically and decide what it means for cost, schedule, permits and crew protection. A usable survey tells you what the material is, where it is, how much there is, in what condition, and how that was established (sampled and analyzed, or presumed). Missing any of those five is a reason to ask questions before bidding.

The federal inspection requirement

For asbestos the federal rule is plain: before demolition begins, the owner or operator must "thoroughly inspect the affected facility or part of the facility where the demolition or renovation operation will occur for the presence of asbestos."[8] If a survey does not cover every part that will be disturbed, it is incomplete for your purposes.

Cal/OSHA also names the places to look: "Pipe-covering insulation, steel beam and column fire protection, and heating, ventilating and air-conditioning duct work shall be surveyed for asbestos."[9] It also says hazardous chemicals, gases, explosives and flammable materials that may have been used in pipes, tanks or equipment on the property must be identified, and when they are apparent or suspected, "testing and purging shall be performed and the hazard eliminated before demolition is started."[9]

What counts as asbestos-containing

Cal/OSHA defines asbestos-containing material (ACM) as "any material containing more than one percent asbestos."[10] It also defines presumed asbestos-containing material (PACM) as "thermal system insulation and surfacing material found in buildings constructed no later than 1980."[10] Presumed means you treat it as asbestos unless it is tested and shown not to be. A survey that says "not tested" on a building constructed in 1980 or earlier is telling you to assume.

Thresholds that change your obligations

The federal demolition rule applies its full set of requirements when the combined amount of regulated asbestos-containing material (RACM) in a building being demolished is "at least 80 linear meters (260 linear feet) on pipes or at least 15 square meters (160 square feet) on other facility components," or "at least 1 cubic meter (35 cubic feet) off facility components" where the length or area could not be measured.[8] Below those amounts, in a building being demolished, the rule still requires notification before demolition, but not the full removal and work-practice package.[8]

California adds its own thresholds. A contractor may not engage in asbestos-related work involving "100 square feet or more of surface area of asbestos containing materials" unless it holds a C-22 Asbestos Abatement classification or its qualifier has passed the asbestos certification examination.[11] Cal/OSHA registration is required for contractors that remove asbestos with fiber content of more than 0.1% and 100 square feet or more of surface area.[12]

Lead and silica in the survey

A hazardous materials survey for demolition is often asbestos-only. The exam expects you to notice what it leaves out. Cal/OSHA's lead standard covers "Demolition or salvage of structures where lead or materials containing lead are present."[13] Its permissible exposure limit is 10 micrograms per cubic meter as an 8-hour average, and its action level is 2 micrograms per cubic meter.[13] Lead-painted surfaces in an older building are common, so "no lead survey" on an old building is a gap to price, not a reason to ignore the question.

Concrete, masonry and mortar release respirable crystalline silica when cut, drilled or broken. The silica standard sets a permissible exposure limit of 50 micrograms per cubic meter as an 8-hour average.[14] Jackhammers and handheld power tools used on silica-containing materials are on the standard's table of specified controls.[14]

Finally, fluorescent lamps and mercury-containing equipment such as thermostats are universal wastes. EPA lists five categories: "batteries, pesticides, mercury-containing equipment, lamps and aerosol cans."[15] A survey that walks the building and counts them is doing you a favor, because they must come out before the building comes down.

Rule 1.2-1 — Survey gaps are priced before the bid, not after the award

When a survey is missing an area, missing a hazard class (asbestos, lead, silica, universal waste, chemicals in tanks and pipes), or is old, the answer is a written question to the owner and, where needed, a supplemental survey. Pricing around an unknown is the cheaper mistake only until the material is found with a crew standing next to it.

Rule 1.2-2 — Compare quantities with the thresholds, component by component

The pipe-insulation threshold is in linear feet; the other-components threshold is in square feet; the off-component threshold is in cubic feet. Each is tested against its own unit. Do not add linear feet to square feet.

Worked example 1.2a — Does the survey put this building above the federal thresholds?

A survey of a building to be demolished reports: 190 linear feet of pipe insulation, 85 square feet of thermal insulation on a boiler and 60 square feet of floor mastic that is friable when disturbed.

  1. Pipe insulation: 190 linear feet is less than 260 linear feet.[8]
  2. Other facility components: 85 + 60 = 145 square feet is less than 160 square feet.[8]
  3. Both are below their thresholds, so only the notification requirements apply under the federal rule, and that notice is due at least 10 working days before demolition begins.[8]
  4. California's rules are separate and use their own measure. The 145 square feet of non-pipe material is already more than 100 square feet of surface area, so the C-22 or certification question and the Cal/OSHA registration question must be answered on their own, whatever the federal result.[11, 12]

The example shows why the exam gives you the thresholds as numbers. A quantity that is only slightly below a threshold on paper is above it after one more room is found.

Worked example 1.2b — Reading a survey for what it does not say

A survey of a 1962 commercial building lists asbestos in floor tile and in the boiler room only. It does not mention pipe insulation, ductwork wrap, steel fireproofing, lead paint or lamps.

  1. The building was constructed in 1962, which is no later than 1980, so thermal system insulation and surfacing material would be presumed asbestos-containing unless tested.[10]
  2. Cal/OSHA names pipe-covering insulation, steel beam and column fire protection and HVAC ductwork as places that must be surveyed.[9]
  3. Demolition is within the lead standard's scope where lead is present.[13]
  4. Conclusion: the survey is incomplete. The estimator asks for a supplemental survey, or prices the pipe, duct and fireproofing as presumed asbestos until tested.

Named traps — hazardous materials surveys

  • Treating a survey as complete because it exists. Check the areas covered against the areas disturbed.
  • Adding unlike units. Linear feet, square feet and cubic feet are separate thresholds.[8]
  • Believing a construction date proves asbestos is absent. The date creates a presumption of asbestos for insulation and surfacing, not an assurance.[10]
  • Thinking "asbestos survey" means "hazardous materials survey". Lead, silica, universal waste and chemicals are separate questions.[9, 13]

Sources cited in this excerpt

  1. CSLB License Examination Study Guide: Building Moving and Demolition (C-21), form 13E-21 (03-2026), for examinations scheduled on or after July 1, 2024. Contractors State License Board (CSLB), 2026-03; read 2026-11-08. https://www.cslb.ca.gov/Resources/StudyGuides/C21StudyGuide.pdf
  2. CSLB Licensing Classifications: C-21 Building Moving/Demolition Contractor (16 CCR section 832.21 text). Contractors State License Board (CSLB), read 2026-11-08. https://www.cslb.ca.gov/About_Us/Library/Licensing_Classifications/Licensing_Classifications_Detail.aspx?Class=C21
  3. 2025 California Building Code (Cal. Code Regs., tit. 24, part 2), Chapter 1 Scope and Administration. California Building Standards Commission (code text via UpCodes), 2025 edition, effective 2026-01-01; read 2026-11-08. https://up.codes/viewer/california/ca-building-code-2025/chapter/1/scope-and-administration
  4. 2025 California Building Code (Cal. Code Regs., tit. 24, part 2), Chapter 33 Safeguards During Construction. California Building Standards Commission (code text via UpCodes), 2025 edition, effective 2026-01-01; read 2026-11-08. https://up.codes/viewer/california/ca-building-code-2025/chapter/33/safeguards-during-construction
  5. Cal. Code Regs., tit. 8, section 1734, Supervision. California Department of Industrial Relations (Cal/OSHA), regulation text, read 2026-11-08. https://www.dir.ca.gov/title8/1734.html
  6. 29 CFR Part 1926 Subpart T, Demolition (sections 1926.850 to 1926.860). U.S. Department of Labor, OSHA (eCFR text), eCFR as of 2026-11-01; read 2026-11-08. https://www.ecfr.gov/current/title-29/part-1926/subpart-T
  7. Cal. Code Regs., tit. 8, section 341, Permits Required. California Department of Industrial Relations (Cal/OSHA), regulation text, read 2026-11-08. https://www.dir.ca.gov/title8/341.html
  8. 40 CFR 61.145 Standard for demolition and renovation (asbestos NESHAP). U.S. Environmental Protection Agency (eCFR text), eCFR as of 2026-11-01; read 2026-11-08. https://www.ecfr.gov/current/title-40/part-61/section-61.145
  9. Cal. Code Regs., tit. 8, section 1735, Demolishing Buildings. California Department of Industrial Relations (Cal/OSHA), regulation text, read 2026-11-08. https://www.dir.ca.gov/title8/1735.html
  10. Cal. Code Regs., tit. 8, section 1529, Asbestos. California Department of Industrial Relations (Cal/OSHA), regulation text, read 2026-11-08. https://www.dir.ca.gov/title8/1529.html
  11. CSLB ASB - Asbestos Certification (Business and Professions Code section 7058.5). Contractors State License Board (CSLB), read 2026-11-08. https://www.cslb.ca.gov/About_Us/Library/Licensing_Classifications/ASB_-_Asbestos_Certification.aspx
  12. Cal/OSHA: Asbestos and Carcinogen Unit (asbestos information). California Department of Industrial Relations, Division of Occupational Safety and Health, read 2026-11-08. https://www.dir.ca.gov/dosh/asbestos.html
  13. Cal. Code Regs., tit. 8, section 1532.1, Lead. California Department of Industrial Relations (Cal/OSHA), regulation text, read 2026-11-08. https://www.dir.ca.gov/title8/1532_1.html
  14. Cal. Code Regs., tit. 8, section 1532.3, Occupational Exposures to Respirable Crystalline Silica. California Department of Industrial Relations (Cal/OSHA), regulation text, read 2026-11-08. https://www.dir.ca.gov/title8/1532_3.html
  15. EPA: Universal Waste. U.S. Environmental Protection Agency, read 2026-11-08. https://www.epa.gov/hw/universal-waste
1

Planning and Estimating

CSLB weights Planning and Estimating at about 25% of the C-21 exam: evaluating plans and specifications, hazardous materials surveys and job site readiness, determining methods and equipment, and estimating costs. Some questions require computation, and a calculator is provided. This page is a short survey; the PrepPass C-21 study guide teaches every statement with worked examples and a full practice exam at CSLB's weights.

25%
2

Project Preparation

CSLB weights Project Preparation at about 20% of the C-21 exam: permitting and notification, mobilizing labor, equipment and materials, developing recycling plans, and removing hazardous materials. This page is a short survey; the PrepPass C-21 study guide teaches the section with worked examples and a full practice exam at CSLB's weights.

20%
3

Building Moving

CSLB weights Building Moving at about 13% of the C-21 exam: moving preparation, determining weight and structural integrity, raising and lowering, and support and transportation. This page is a short survey; the PrepPass C-21 study guide teaches the section with worked examples and a full practice exam at CSLB's weights.

13%
4

Structure Demolition

CSLB weights Structure Demolition at about 21% of the C-21 exam: pre-demolition site preparation, demolishing single- and multi-story structures, separating materials, transporting debris, and cleaning and backfilling. This page is a short survey; the PrepPass C-21 study guide teaches the section with worked examples and a full practice exam at CSLB's weights.

21%
5

Safety

CSLB weights Safety at about 21% of the C-21 exam: job site safety, personnel safety, traffic controls and personal protective equipment. This page is a short survey; the PrepPass C-21 study guide teaches the section with worked examples and a full practice exam at CSLB's weights.

21%

Practice by topic

Jump straight into free practice questions for any single CSLB C-21 Building Moving and Demolition (Trade Exam) topic.

Studying in order?

Practice stays free. The full CSLB C-21 Building Moving and Demolition study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.

Get the book — $24.99