26 questions

Steep-Slope Roof Projects

What is the minimum number of fasteners for an individual (non-strip) asphalt shingle?

  • a.Two✓
  • b.Four
  • c.One
  • d.Six

The CRC requires at least the manufacturer's number of fasteners, but not less than four per strip shingle or two per individual shingle.2025 CRC R905.2.6

Steep-Slope Roof Projects

What minimum head diameter must an asphalt shingle roofing nail have?

  • a.3/8 inch✓
  • b.5/16 inch
  • c.1/2 inch
  • d.1/4 inch

Asphalt shingle nails need a minimum 3/8-inch-diameter head and a 12-gage shank. The 5/16-inch head is the tile nail minimum.2025 CRC R905.2.5

Steep-Slope Roof Projects

What minimum shank size must an asphalt shingle roofing nail have?

  • a.12-gage✓
  • b.18-gage
  • c.14-gage
  • d.16-gage

Asphalt shingle fasteners need at least a 12-gage [0.105 inch] shank. The 11-gage figure is the minimum for tile nails.2025 CRC R905.2.5

Steep-Slope Roof Projects

To which standard must asphalt shingles comply under the CRC?

  • a.ASTM D226
  • b.ASTM C406
  • c.ASTM D3462✓
  • d.ASTM D3909

Asphalt shingles comply with ASTM D3462. D226 is felt underlayment, D3909 mineral-surfaced roll roofing and C406 slate.2025 CRC R905.2.4

Steep-Slope Roof Projects

Concrete tile is installed at 3:12. What underlayment application is required?

  • a.Double underlayment✓
  • b.A single layer lapped 2 inches
  • c.Self-adhered membrane at the eaves only
  • d.No underlayment

For tile slopes from 2-1/2:12 to 4:12, double underlayment application is required. A single layer lapped 2 inches is the method at 4:12 and steeper.2025 CRC R905.3.2

Steep-Slope Roof Projects

In an area designated for ice barriers, which building does NOT need one?

  • a.A two-story house
  • b.A house with a 12:12 roof
  • c.A detached unheated shed✓
  • d.A heated garage attached to a house

The ice barrier requirement has an exception for detached accessory structures not containing conditioned floor area.2025 CRC R905.1.2 exception

Steep-Slope Roof Projects

Step flashing is installed where shingles meet a wall covered with lap siding. Where does the flashing's vertical leg go?

  • a.On top of the siding, sealed
  • b.Behind the sheathing
  • c.Cut off at the siding's bottom edge
  • d.Continuous under the siding✓

Where siding is provided on the vertical sidewall, the vertical leg of the sidewall flashing must be continuous under the siding.2025 CRC R905.2.8.3

Steep-Slope Roof Projects

What is the minimum thickness of corrosion-resistant metal cap flashing on an asphalt shingle roof?

  • a.0.032 inch
  • b.0.019 inch✓
  • c.0.010 inch
  • d.0.0125 inch

Cap flashing must be corrosion-resistant metal of minimum nominal 0.019-inch thickness, the same minimum as metal base flashing.2025 CRC R905.2.8.1

Steep-Slope Roof Projects

When must valley linings be installed on an asphalt shingle roof?

  • a.After the shingles, as a cover
  • b.Before the shingles✓
  • c.Only on slopes below 4:12
  • d.Only when the valley is closed

Valley linings shall be installed in accordance with the manufacturer's instructions before applying shingles.2025 CRC R905.2.8.2

Steep-Slope Roof Projects

Which copper valley lining meets the CRC table for asphalt shingle open valleys?

  • a.Copper-colored paint on steel
  • b.Copper foil tape
  • c.16 oz cold-rolled copper✓
  • d.8 oz copper sheet

The table lists cold-rolled copper of 0.0216 inch nominal, ASTM B370, 16 oz per square foot (and high-yield copper at 12 oz).2025 CRC Table R905.2.8.2

Want these explained in order? CSLB C-39 Roofing Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Steep-Slope Roof Projects

What minimum height must the splash diverter rib on clay tile valley flashing have?

  • a.2 inches
  • b.3/4 inch
  • c.1/2 inch
  • d.1 inch✓

Tile valley flashing extends at least 11 inches each way and has a splash diverter rib at least 1 inch high. The 3/4-inch rib is the metal roof shingle rule.2025 CRC R905.3.9

Steep-Slope Roof Projects

What minimum head size must a nail for clay or concrete tile have?

  • a.5/16 inch✓
  • b.3/8 inch
  • c.1/4 inch
  • d.1/2 inch

Tile nails must be at least 11-gage with a 5/16-inch head. The 3/8-inch head is the asphalt shingle rule.2025 CRC R905.3.7

Steep-Slope Roof Projects

Concrete tile is installed in an area subject to snow. How many fasteners per tile are required at minimum?

  • a.One
  • b.One on every other row
  • c.None below 5:12
  • d.Two✓

In areas subject to snow, not less than two fasteners per tile are required.2025 CRC R905.3.8

Steep-Slope Roof Projects

Concrete tile is laid on solid sheathing without battens at 3:12 (no snow, no wind design, tile over 9 psf). How are field tiles fastened?

  • a.Two fasteners per tile
  • b.One fastener per tile✓
  • c.No fasteners needed below 5:12
  • d.One fastener every other row

On solid sheathing without battens, the table requires one fastener per tile at all slopes. The no-fastener entry below 5:12 applies to spaced sheathing or solid sheathing with battens.2025 CRC Table R905.3.8

Steep-Slope Roof Projects

Which ASTM standard must roofing slate meet under the CRC?

  • a.ASTM C1167
  • b.ASTM D3462
  • c.ASTM C1492
  • d.ASTM C406✓

Slate shingles comply with ASTM C406. C1167 is clay tile, C1492 concrete tile and D3462 asphalt shingles.2025 CRC R905.6.4

Steep-Slope Roof Projects

What minimum metal does the CRC require for slate valley and flashing metal?

  • a.Any painted steel
  • b.0.0179-inch G90 steel✓
  • c.0.0125-inch G60 steel
  • d.0.010-inch aluminum

Slate valley and flashing metal must be a minimum uncoated thickness of 0.0179 inch, zinc-coated G90, and valley flashing at least 15 inches wide.2025 CRC R905.6.7

Steep-Slope Roof Projects

Slate is installed on a very steep 22:12 mansard. What minimum headlap does the table require?

  • a.6 inches
  • b.3 inches
  • c.2 inches✓
  • d.4 inches

At slopes of 20:12 and steeper the minimum slate headlap is 2 inches; 3 inches applies from 8:12 to below 20:12 and 4 inches from 4:12 to below 8:12.2025 CRC Table R905.6.6

Steep-Slope Roof Projects

Which rule applies to joints in wood shingle courses?

  • a.Only the starter course has a joint rule
  • b.Joints must line up every other course
  • c.No joints aligned in any three adjacent courses✓
  • d.Joints may align if they are sealed

Wood shingles are laid with a side lap of at least 1-1/2 inches between joints in courses, and no two joints may be in direct alignment in any three adjacent courses.2025 CRC R905.7.6

Steep-Slope Roof Projects

Which nail does the table specify for 24-inch wood shingles?

  • a.4d box nails✓
  • b.3d box nails
  • c.8d common nails
  • d.6d box nails

The table specifies 3d box nails for 16- and 18-inch shingles and 4d box nails (1-1/2 in x 0.076) for 24-inch shingles.2025 CRC Table R905.7.6(2)

Steep-Slope Roof Projects

What is the minimum felt used as interlayment strips between courses of wood shakes?

  • a.18-inch strips of No. 30 felt✓
  • b.12-inch strips of No. 15 felt
  • c.Self-adhered membrane strips
  • d.36-inch strips of house wrap

Shakes are interlaid with 18-inch-wide strips of not less than No. 30 felt, positioned so the felt is not exposed to the weather.2025 CRC R905.8.8

Want these explained in order? CSLB C-39 Roofing Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Steep-Slope Roof Projects

What minimum grade must naturally durable wood shakes meet?

  • a.No. 3
  • b.No. 1✓
  • c.No. 2
  • d.Any grade if labeled

The shake material table requires No. 1 grade for wood shakes of naturally durable wood under the Cedar Shake and Shingle Bureau rules.2025 CRC Table R905.8.5

Steep-Slope Roof Projects

What is the minimum slope for a lapped, nonsoldered-seam metal roof installed without lap sealant?

  • a.1/2:12
  • b.2:12
  • c.3:12✓
  • d.1/4:12

Lapped, nonsoldered-seam metal roofs without applied lap sealant need a 3:12 slope; with lap sealant, 1/2:12; standing seam, 1/4:12.2025 CRC R905.10.2

Steep-Slope Roof Projects

What minimum weight does the CRC table set for cold-rolled copper sheet roofing (not high-yield)?

  • a.8 oz per sq ft
  • b.16 oz per sq ft✓
  • c.20 oz per sq ft
  • d.12 oz per sq ft

The metal roof covering table sets ASTM B370 copper at a minimum of 16 oz/sq ft, or 12 oz/sq ft for high-yield copper.2025 CRC Table R905.10.3(1)

Steep-Slope Roof Projects

Where must required attic ventilation openings open?

  • a.Into the garage
  • b.Directly outdoors✓
  • c.Into the living space
  • d.Into a wall cavity

Required ventilation openings must open directly to the outside air and be protected against birds, rodents, snakes and similar creatures.2025 CRC R806.1

Steep-Slope Roof Projects

How does the NPS clay tile brief describe removing a single broken tile?

  • a.Break it out with a hammer from above
  • b.Pry up the course above with a crowbar
  • c.Leave it and seal the crack
  • d.Cut its nails with a ripper or hacksaw blade✓

The NPS says a broken tile should be carefully removed with a slate ripper or hacksaw blade inserted under the tile to cut the nails holding it.NPS Preservation Brief 30

Steep-Slope Roof Projects

Why does the NPS say slate should be laid with copper or stainless steel nails?

  • a.Steel nails crack the slate when driven
  • b.Stainless nails need no pre-punched holes
  • c.Copper nails are cheaper
  • d.Steel nails rust out first✓

The NPS explains that plain steel and galvanized nails usually rust out long before the slate begins to deteriorate, which is a common cause of slate loss.NPS Preservation Brief 29