CSLB C-8 Concrete (Trade Exam) — All Questions
28 questions
A shed slab is 16 ft by 20 ft and 4 in thick. How much concrete does it contain?
- a.About 3.5 cubic yards
- b.About 4.0 cubic yards✓
- c.About 47.4 cubic yards
- d.About 11.9 cubic yards
16 × 20 = 320 sq ft; 4 in = 0.333 ft; 320 × 0.333 = 106.7 cu ft; ÷ 27 = 4.0 cu yd. Dividing by 9 gives 11.9, and multiplying by 4 without converting inches gives 47.4.NIST Handbook 44 (2026), Appendix C
A sidewalk is 5 ft wide, 120 ft long and 4 in thick. How much concrete does it need?
- a.About 6.2 cubic yards
- b.About 22.2 cubic yards
- c.About 88.9 cubic yards
- d.About 7.4 cubic yards✓
5 × 120 = 600 sq ft × 0.333 ft = 200 cu ft ÷ 27 = 7.4 cu yd. 22.2 comes from dividing by 9 instead of 27, and 88.9 from treating 4 in as 4 ft.NIST Handbook 44 (2026), Appendix C
About how many square feet does one cubic yard of concrete cover at 4 inches thick?
- a.81 square feet✓
- b.324 square feet
- c.27 square feet
- d.108 square feet
One cubic yard is 27 cu ft; 27 ÷ 0.333 ft = 81 sq ft. 27 is the cubic feet in a yard, not the area it covers, and 324 comes from multiplying by 12 instead of dividing by the thickness in feet.NIST Handbook 44 (2026), Appendix C
About how many square feet does one cubic yard of concrete cover at 6 inches thick?
- a.54 square feet✓
- b.162 square feet
- c.81 square feet
- d.36 square feet
27 cu ft ÷ 0.5 ft = 54 sq ft. 81 sq ft is the coverage at 4 in; a thicker slab covers less area per yard, not more.NIST Handbook 44 (2026), Appendix C
Twelve piers are 12 in in diameter and 6 ft deep. About how much concrete do they take?
- a.About 6.3 cubic yards
- b.About 8.4 cubic yards
- c.About 2.1 cubic yards✓
- d.About 2.7 cubic yards
Area = 0.785 × 1² = 0.785 sq ft; one pier = 0.785 × 6 = 4.71 cu ft; twelve = 56.5 cu ft ÷ 27 = 2.1 cu yd. Treating each pier as a 1-ft square gives 2.7, and using the diameter as the radius gives 8.4.NIST Handbook 44 (2026), Appendix C
A continuous footing is 24 in wide and 12 in deep with a centerline length of 150 ft. How much concrete does it hold?
- a.About 11.1 cubic yards✓
- b.About 33.3 cubic yards
- c.About 5.6 cubic yards
- d.About 13.3 cubic yards
150 × 2 × 1 = 300 cu ft ÷ 27 = 11.1 cu yd. Dividing by 9 gives 33.3, and using a 12-in width by mistake gives 5.6.NIST Handbook 44 (2026), Appendix C
Bars will be spaced 18 in on center across a 30-ft-wide slab. How many bars run the other way?
- a.22
- b.18
- c.21✓
- d.20
30 ft = 360 in; 360 ÷ 18 = 20 spaces; bars = spaces + 1 = 21. Answering 20 counts the spaces rather than the bars.NIST Handbook 44 (2026), Appendix C
What is the nominal diameter of a #7 reinforcing bar?
- a.7 millimeters
- b.7/16 inch
- c.7/8 inch✓
- d.3/4 inch
U.S. bar sizes are identified in eighths of an inch, so #7 is 7/8 in. 3/4 in is a #6, and reading the number as sixteenths or millimeters is a common error.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 4
A takeoff totals 1,350 cubic feet of concrete. How many cubic yards is that?
- a.150 cubic yards
- b.112.5 cubic yards
- c.45 cubic yards
- d.50 cubic yards✓
1,350 ÷ 27 = 50 cu yd. Dividing by 9 gives 150, and dividing by 12 gives 112.5, neither of which converts cubic feet to cubic yards.NIST Handbook 44 (2026), Appendix C
A square column is 12 in by 12 in and 10 ft tall. How much form contact area do its four sides need?
- a.10 square feet
- b.40 square feet✓
- c.120 square feet
- d.20 square feet
Each side is 1 ft × 10 ft = 10 sq ft, and four sides give 40 sq ft. 10 sq ft is one side, and 120 comes from using inches for the side width.Estimating practice (form contact area)
Want these explained in order? CSLB C-8 Concrete Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
A 23-cubic-yard pour will come in trucks carrying 10 cubic yards each. How many loads must be ordered?
- a.4
- b.2
- c.1
- d.3✓
23 ÷ 10 = 2.3, and a partial load is still a truck, so 3 loads. Two loads bring only 20 cu yd.NIST Handbook 44 (2026), Appendix C
A single, stand-alone project will disturb 30,000 square feet of soil and is not part of a larger plan. Does it need state Construction Stormwater General Permit coverage?
- a.No, it is under one acre.✓
- b.Yes, over 10,000 square feet needs it.
- c.Only if it is a public project.
- d.Yes, all grading needs coverage.
One acre is 43,560 sq ft; the State Water Board's permit applies to projects disturbing one or more acres, or less if part of a larger common plan that disturbs an acre. Local stormwater rules still apply.State Water Resources Control Board, Order 2022-0057-DWQ
On public concrete work, what does a "rebar factor" describe?
- a.Average pounds of rebar per cubic yard✓
- b.The ratio of bar length to lap length
- c.The yield strength of the steel
- d.The number of bars per square foot
Caltrans describes establishing the average pounds of rebar per cubic yard of a concrete item, the "rebar factor," to pay for reinforcement in step with concrete quantities. Yield strength is shown by the grade mark.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 2
A winter pour needs faster setting. Which ASTM C494 admixture type accelerates?
- a.Type C✓
- b.Type D
- c.Type B
- d.Type F
Type C is accelerating. Type B and Type D retard setting, which is the opposite of what a cold pour needs, and Type F is a high-range water reducer.IMCP Manual for Concrete Pavement, 2nd ed. (FHWA/CP Tech Center, 2019)
Which portland cement type offers moderate sulfate resistance?
- a.Type IV
- b.Type III
- c.Type I
- d.Type II✓
Type II is moderate sulfate resistance (Type V is high). Type III is high early strength and Type IV is low heat of hydration.IMCP Manual for Concrete Pavement, 2nd ed. (FHWA/CP Tech Center, 2019)
Why is an air-entraining admixture specified for exterior concrete in freezing areas?
- a.To reduce the need for curing
- b.To speed up the set
- c.To raise the compressive strength
- d.For freeze-thaw and scaling resistance✓
Air-entraining admixtures stabilize microscopic bubbles that provide freeze-thaw resistance and improve resistance to deicer salt scaling. They do not raise strength, speed setting or replace curing.IMCP Manual for Concrete Pavement, 2nd ed. (FHWA/CP Tech Center, 2019)
A load has stiffened in the truck. The driver offers to add water and remix it. What is the rule?
- a.It may be re-tempered if the slump is low.
- b.It may be re-tempered below 90 °F.
- c.It may be re-tempered once.
- d.Re-tempering it with water is prohibited.✓
Caltrans states that re-tempering partially hardened concrete with additional water is expressly prohibited, because it can markedly reduce strength. Low slump from stiffening is the symptom, not a reason to add water.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
A load without a retarder is 95 minutes from batching and has turned 200 drum revolutions. Under the Caltrans limits, may it be placed?
- a.No, it is past 90 minutes.✓
- b.Yes, it is under 250 revolutions.
- c.Yes, if it is placed quickly.
- d.Yes, the limit is 120 minutes.
Without a retarder the limit is 250 revolutions or 90 minutes, whichever occurs first; 95 minutes exceeds the time limit even though the revolutions are under 250. The 120-minute limit applies only with a retarder.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
Water held back at the plant is added to a truck on site within the mix design. What must happen before discharge continues?
- a.Add an equal amount of cement
- b.Mix at least 30 drum revolutions✓
- c.Wait 30 minutes for it to absorb
- d.Mix for at least 5 revolutions
Caltrans requires added water to be introduced only once and mixed for at least 30 drum revolutions before more than a quarter cubic yard of the load has been discharged. Waiting without mixing does not blend it.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
Which item belongs on the equipment list for a large wall pour, in case of breakdown?
- a.Extra form oil
- b.A spare slump cone
- c.A second finishing crew only
- d.A standby vibrator and generator✓
Caltrans calls it best practice to always have a standby vibrator and generator on hand, and lists backup equipment among pre-pour items. A breakdown with no spare leaves unconsolidated concrete and cold joints.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
Want these explained in order? CSLB C-8 Concrete Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Why might a pump be chosen over a crane and bucket under a low roof or canopy?
- a.Pumps allow water to be added.
- b.Pumps need less overhead clearance.✓
- c.Pumps place concrete more slowly.
- d.Pumps need no setup inspection.
Caltrans notes that pumps normally require less headroom than a crane and bucket. Pumps also place faster, and they still require inspection and follow the water limits.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
What is the main placing drawback of a belt conveyor?
- a.It cannot reach more than 20 feet
- b.It requires aluminum pipe
- c.Segregation where it transfers✓
- d.It only works with low slump
Caltrans identifies a tendency for concrete to segregate at intermediate transfer points and at the discharge point as a major disadvantage of belts; hoppers or baffles at discharge help.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
Heavy rain begins on a slab being placed. What is the concern for the surface?
- a.Rain speeds up the set.
- b.Rain only matters after finishing.
- c.Rain improves surface strength.
- d.Diluted paste, higher w/c ratio✓
Rain dilutes the mortar at the surface and may increase the water-cement ratio enough to decrease strength and durability there, so placement should be protected or suspended.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5
A plan sheet references a standard detail from a Standard Plans book. How binding is that detail?
- a.It is part of the contract.✓
- b.It is only a suggestion.
- c.It is binding only on public work.
- d.It applies only if drawn on the sheet.
Caltrans states that Standard Plans are contractual supplements to the project plans; a referenced detail is as binding as the sheet. On any job, referenced details are part of the documents you build to.Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 2
Workers will enter a 4-ft-deep footing trench. Does the trench need a Cal/OSHA excavation permit?
- a.Yes, if it is longer than 50 ft.
- b.Only if the soil is Type C.
- c.Yes, every entered trench needs one.
- d.No; that permit starts at 5 ft.✓
Title 8 §341 requires a permit for trenches or excavations 5 feet or deeper into which any person must descend. A 4-ft trench still needs a competent person's check for cave-in signs, but no permit.Cal. Code Regs. tit. 8, §341
An excavator's 811 ticket expires while trenching is still going on. What must happen?
- a.Keep going if marks are visible.
- b.Finish that day, then renew.
- c.Call the operator directly instead.
- d.Stop and get a new ticket.✓
If a ticket expires while work is ongoing, the excavator must immediately cease excavation, contact the regional notification center and get a new ticket before resuming.Cal. Gov. Code §§4216–4216.9
An applicant has 2 years at an accredited construction program and 3 years as a journey-level concrete finisher. How much of the program can count toward the 4-year requirement?
- a.Only 6 months per year attended
- b.None, school never counts
- c.All of it, plus up to 4 years
- d.Up to 2 years; never over 3✓
Under 16 CCR §825, accredited training or apprenticeship can count as experience, but never for more than 3 years; here the 2 years can count, giving 5 years total.Cal. Code Regs. tit. 16, §825
Which field change lowers concrete strength the most directly?
- a.Consolidating with a vibrator
- b.Curing for the full specified time
- c.Using a water-reducing admixture
- d.Water beyond the mix design✓
Strength increases as the water-cementitious ratio decreases, so water beyond the mix design raises the ratio and lowers strength. Water reducers, curing and vibration all help strength.IMCP Manual for Concrete Pavement, 2nd ed. (FHWA/CP Tech Center, 2019)