CSLB C-8 Concrete (Trade Exam) Practice Test

Studying in order?

Practice stays free. The full CSLB C-8 Concrete study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.

Get the book — $24.99
CSLB Concrete (C-8) Trade Examination — Exam facts
Administering bodyContractors State License Board (CSLB), California Department of Consumer Affairs — exam delivered by PSI Services LLC

Source: CSLB — Examinations Frequently Asked Questions

QuestionsNot published by CSLB

What we read and found nothing in: CSLB — Step 7: Studying for the Examination

Time limit210 minutes

Source: CSLB — Examinations Frequently Asked Questions

Passing scoreNot published by CSLB

What we read and found nothing in: CSLB — Step 7: Studying for the Examination

Fees
  • $450 — Original application (exam or waiver, one classification) (CSLB, one-time)
  • $51.43 — Examination registration (each registration, first attempt or retake) (PSI Services LLC, per attempt)
  • $200 — Initial license fee (sole owner) (CSLB, one-time)
  • $350 — Initial license fee (non-sole owner: partnership, corporation, LLC, joint venture) (CSLB, one-time)

Source: CSLB — List of All CSLB Fees

Languages offeredEnglish · Spanish

Source: CSLB — Examinations Frequently Asked Questions

Exam facts, with a source for every line

Frequently asked questions

How many CSLB Trade — Concrete (C-8) practice questions are here?+

A full bank of original CSLB Trade — Concrete (C-8) practice questions across the official content areas, weighted like the real exam, with explanations. Free, no signup.

What is the CSLB Trade — Concrete (C-8) exam like?+

A multiple-choice exam, 210 minutes. Practice by topic here, then take the full timed mock exam to gauge readiness.

Are these the real exam questions?+

No. Every question is 100% original, written from public primary sources with explanations. We never copy real exam questions or paid prep material.

Can I study in Chinese or Spanish?+

PrepPass practice is in English, 中文 and Español. The official exam is in English — switch the question language to English any time to rehearse the exact terminology you'll see on test day.

Is there a study guide for the CSLB Trade — Concrete (C-8)?+

Yes. PrepPass sells CSLB C-8 Concrete Trade Exam Study Guide (2026), a PDF + EPUB download, $24.99 one-time; the practice on this page stays free without it. See the study guide →

Sample practice questions

A few real questions from this free bank, with full explanations. Use the practice tool above for the whole set.

  1. 1. Planning and Estimating

    A shed slab is 16 ft by 20 ft and 4 in thick. How much concrete does it contain?

    • a.About 3.5 cubic yards
    • b.About 4.0 cubic yards
    • c.About 47.4 cubic yards
    • d.About 11.9 cubic yards

    Answer: b

    Explanation: 16 × 20 = 320 sq ft; 4 in = 0.333 ft; 320 × 0.333 = 106.7 cu ft; ÷ 27 = 4.0 cu yd. Dividing by 9 gives 11.9, and multiplying by 4 without converting inches gives 47.4.

    Source: NIST Handbook 44 (2026), Appendix C

  2. 2. Planning and Estimating

    A 23-cubic-yard pour will come in trucks carrying 10 cubic yards each. How many loads must be ordered?

    • a.4
    • b.2
    • c.1
    • d.3

    Answer: d

    Explanation: 23 ÷ 10 = 2.3, and a partial load is still a truck, so 3 loads. Two loads bring only 20 cu yd.

    Source: NIST Handbook 44 (2026), Appendix C

  3. 3. Planning and Estimating

    Why might a pump be chosen over a crane and bucket under a low roof or canopy?

    • a.Pumps allow water to be added.
    • b.Pumps need less overhead clearance.
    • c.Pumps place concrete more slowly.
    • d.Pumps need no setup inspection.

    Answer: b

    Explanation: Caltrans notes that pumps normally require less headroom than a crane and bucket. Pumps also place faster, and they still require inspection and follow the water limits.

    Source: Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5

  4. 4. Pre-placement Preparation

    A dry, semi-porous subgrade will receive a footing. What does the federal guide specification say to do?

    • a.Flood it to 2 inches deep.
    • b.Cover it with dry cement.
    • c.Leave it dry for better bond.
    • d.Sprinkle it to eliminate suction.

    Answer: d

    Explanation: The specification says to sprinkle a semi-porous, dry subgrade to eliminate suction when concrete is deposited, or seal it with the specified vapor retarder. Flooding leaves standing water, which must be removed.

    Source: UFGS 03 30 00 Cast-in-Place Concrete (Chg 10, Aug 2025)

  5. 5. Pre-placement Preparation

    A rectangular form layout measures 36 ft and 40 ft on its two diagonals. What does that tell you?

    • a.Only the sides are wrong.
    • b.The slab is 38 ft long.
    • c.The layout is square.
    • d.The layout is not square.

    Answer: d

    Explanation: A true rectangle has equal diagonals; unequal diagonals mean the layout is a parallelogram and a corner is out of square.

    Source: Field layout practice (rectangle geometry)

  6. 6. Pre-placement Preparation

    On a Caltrans job, the plans do not state the clear cover for a formed retaining wall. What cover does Caltrans describe as typical?

    • a.2 inches minimum
    • b.3/4 inch minimum
    • c.No cover is needed
    • d.6 inches minimum

    Answer: a

    Explanation: Caltrans states clear cover is typically 2 inches minimum unless specified otherwise, with more for cast-in-drilled-hole piles (3 in) and severe environments. Three-quarters of an inch is an interior-slab value in other specifications.

    Source: Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 4

  7. 7. Placing and Finishing

    Concrete is placed around epoxy-coated reinforcement. What kind of vibrator head is required?

    • a.A rubber- or plastic-coated one
    • b.A bare steel head only
    • c.No vibrator may be used
    • d.An oversized steel head

    Answer: a

    Explanation: Where epoxy-coated rebar is used, vibrators must be coated with plastic or hard rubber to avoid damaging the coating.

    Source: Caltrans Reinforced Concrete Construction Manual (June 2025), ch. 5

  8. 8. Placing and Finishing

    Which ASTM standard does the federal guide specification cite for sampling freshly mixed concrete?

    • a.ASTM C143
    • b.ASTM C172
    • c.ASTM C1074
    • d.ASTM C39

    Answer: b

    Explanation: The specification collects samples of fresh concrete per ASTM C172. C39 is the compression test of cylinders, C143 the slump test, and C1074 the maturity method.

    Source: UFGS 03 30 00 Cast-in-Place Concrete (Chg 10, Aug 2025)

  9. 9. Safety

    What must a construction employer's first-aid kit be kept in?

    • a.A locked office cabinet
    • b.The foreman's truck only
    • c.A weatherproof container
    • d.Any cardboard box

    Answer: c

    Explanation: Title 8 §1512 requires at least one first-aid kit in a weatherproof container, regularly inspected and restocked.

    Source: Cal. Code Regs. tit. 8, §1512

  10. 10. Safety

    Where must the mid-rail of a standard guardrail be?

    • a.Anywhere below 30 inches
    • b.Halfway between top rail and floor
    • c.At the same height as the top rail
    • d.Six inches above the floor

    Answer: b

    Explanation: Title 8 §1620 places the mid-rail halfway between the top rail and the floor, platform, runway or ramp.

    Source: Cal. Code Regs. tit. 8, §1620