A subcontractor abandons a project after pouring a defective foundation and refuses to return calls or correct the defects, leaving the owner to hire someone else at greater cost. Which provision most directly supports CSLB discipline?

a.§7108 — diverting funds received for the project elsewhere
b.§7113 — not completing the project for the contract price
c.§7159 — omitting a required term from the written contract
d.§7068.2 — failing to report the qualifier's disassociation

Explanation

B&P §7113 makes a licensee's failure in a material respect to complete a construction project for the price stated in the contract a cause for discipline, which is exactly what the owner's higher completion cost evidences. (a) would require evidence that project money went somewhere else, and nothing in the facts says it did. (c) polices the paperwork of the contract, not the performance of it. (d) is a reporting duty about the qualifying individual and has nothing to do with abandoned work.

Law Reference: Bus. & Prof. Code §7113

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report