Business FinancesQuestion 659 of 690
Under Bus. & Prof. Code §7071.11, when claims against a contractor's $25,000 license bond exceed the bond's penal sum, the bond proceeds are distributed in which order of priority?
a.First-in-time, first-in-right by claim filing date
b.Pro rata among all valid claimants, regardless of category
c.First to claims for wages and benefits (employees and trust funds), then to consumer claims by residential property owners, then to other claimants — with valid claims within each priority sharing pro rata if insufficient
d.First to the surety to recoup premium, then to the CSLB for fines, then to claimants
Explanation
Bus. & Prof. Code §7071.11 establishes a tiered priority for distributing license-bond proceeds when claims exceed the $25,000 penal sum: (1) employee wage/benefit/trust-fund claims, (2) damages to a residential property owner under a home improvement contract who paid for work not completed, (3) damages to a non-residential property owner, and (4) other valid claims. Within each priority, pro rata sharing applies if proceeds are insufficient. First-in-time rules apply to mechanics' liens, not §7071.11 bond distributions. The surety/CSLB priority option is not in the statute.
Law Reference: Bus. & Prof. Code §7071.11Practice all 690 questions free — no signup required.
Related questions on this topic
- Under California home improvement contract law, the down payment a contractor may collect from an owner before any work is done or materials are delivered is limited to:
- On a residential swimming pool contract, what is the maximum down payment a contractor may receive before work begins?
- A consumer wins a final judgment of $50,000 against a licensed contractor for fraudulent home improvement work. The CSLB license bond is $25,000. What is the most the claimant can recover from the bond itself?
- Instead of filing a contractor's license bond, a licensee may deposit cash or equivalent securities with the State Treasurer under Bus. & Prof. Code §7071.12. To replace the $25,000 license bond entirely with cash, the licensee must deposit:
- A Responsible Managing Employee (RME) differs from a Responsible Managing Officer (RMO) in that an RME must:
- A general contractor classifies its on-site framer as an independent contractor and issues a 1099-NEC instead of a W-2. If the framer is later determined to be a W-2 employee under AB-5 and federal common-law tests, the general contractor will likely be liable for: