On a federal public works project, the prevailing wage requirement comes primarily from the:
Explanation
On a federally funded construction contract above the statutory threshold, the Davis-Bacon Act requires the locally prevailing wages and fringe benefits determined by the U.S. Department of Labor. California's Labor Code prevailing wage scheme attaches to state and local public works; it does not travel onto a federal project merely because the work is in California. Article 2 of the Commercial Code governs sales of goods and says nothing about wages. B&P §7108 concerns diversion of funds by a licensee, not wage rates.
Law Reference: 40 U.S.C. §3142 (Davis-Bacon Act)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:
- A city hires a contractor for a $50,000 public sidewalk repair. Regarding prevailing wages, the contractor must:
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
- The performance bond on a public works project protects the:
- DIR public works contractor registration generally must be:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
Last reviewed: · editorial process