Public WorksQuestion 1600 of 1605
DIR public works contractor registration generally must be:
a.Waived for licensed contractors
b.Obtained once and never renewed
c.Renewed periodically (annually) and kept current to bid and work on covered public works
d.Obtained only after the project is complete
Explanation
Labor Code §1725.5 requires DIR public works registration to be maintained on a current basis (renewed on the annual cycle) for a contractor to bid on, be listed on a bid for, and perform covered public works. A lapse can disqualify the contractor.
Law Reference: Labor Code §1725.5Practice all 1605 questions free — no signup required.
Related questions on this topic
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
- On a federal public works project, the prevailing wage requirement comes primarily from the:
- The performance bond on a public works project protects the:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
- When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
- On a public works project, the prevailing wage obligation applies to:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)