The performance bond on a public works project protects the:
Explanation
The performance bond names the public agency as obligee and guarantees that the work will be completed according to the contract; if the contractor defaults, the surety arranges completion or pays damages up to the penal sum. Unpaid subs and suppliers look instead to the payment bond required by Civil Code §9550 and to a stop payment notice. A surety bond is not insurance for the principal: it never indemnifies the contractor against its own defective work, and the surety may seek reimbursement from the contractor after paying. Delay damages against the agency are a contract claim, not a bond promise.
Law Reference: Public Contract Code §20170; Civil Code §9550This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A city hires a contractor for a $50,000 public sidewalk repair. Regarding prevailing wages, the contractor must:
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
- On a federal public works project, the prevailing wage requirement comes primarily from the:
- DIR public works contractor registration generally must be:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
- When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
Last reviewed: · editorial process