Contracts & ExecutionQuestion 691 of 1605
A homeowner hires a licensed contractor to remodel a kitchen for $18,000. At what contract price does California law require that a home improvement contract be put in writing?
a.Only contracts over $25,000 must be written
b.Any amount over $500 (labor and materials combined)
c.Any amount over $2,500
d.Any amount over $5,000
Explanation
Under B&P §7159, a home improvement contract and any changes to it must be in writing whenever the aggregate contract price, including labor and materials, exceeds $500.
Law Reference: B&P §7159Practice all 1605 questions free — no signup required.
Related questions on this topic
- Bus. & Prof. Code §7159.5 limits progress payments on a home improvement contract such that, at any given time during the project, the amount paid by the owner may not exceed:
- A contractor solicits a home improvement contract at the homeowner's residence following a door-to-door knock. Under Civil Code §1689.7 (the Home Solicitation Sales Act), the homeowner generally has the right to cancel the contract:
- On a private construction project, a direct contractor wants to enforce a 'pay-when-paid' clause to delay payment to a subcontractor by 90 days while waiting for the owner to pay. Under California prompt-payment law, this clause is generally:
- Which of the following projects is NOT considered a 'home improvement' under the Contractors State License Law?
- A contractor begins demolishing a homeowner's bathroom before the written home improvement contract is signed. Under the Contractors State License Law, this is:
- A home improvement contract has a total price of $6,000. What is the maximum down payment the contractor may lawfully require?
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)