Which scenario would DISQUALIFY a job from using the service and repair contract form?

a.The final price is $1,500 for the requested repair
b.The total is $600 and paid on completion
c.The homeowner phoned to request the repair
d.No down payment is collected

Explanation

A service and repair contract requires the price to be $750 or less. A $1,500 job exceeds that limit and must use a full home improvement contract.

Law Reference: B&P §7159.10

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report