Contracts & ExecutionQuestion 698 of 1605

A contractor structures a home improvement contract so that each progress payment is due 'as work proceeds.' Under §7159, each progress payment must:

a.Be collected only at project completion
b.Not exceed the value of the work performed or materials delivered at that point
c.Be at least $5,000 to be enforceable
d.Equal one-third of the total contract price

Explanation

B&P §7159 requires that progress payments be tied to specifically described phases and that a contractor not request or accept payment exceeding the value of work performed or materials delivered.

Law Reference: B&P §7159(d)