Who holds ultimate accountability for the project's success and owns the business case?
- a.The Executive✓
- b.The Project Manager
- c.The Senior User
- d.The Team Manager
The Executive is ultimately accountable for the project, supported by the wider Project Board, and owns the business case to ensure the project stays value-for-money and justified throughout.
Which three roles make up the Project Board?
- a.Project Manager, Team Manager and Project Support
- b.Executive, Senior User and Senior Supplier✓
- c.Executive, Project Manager and Project Assurance
- d.Senior User, Change Authority and Team Manager
The Project Board comprises the Executive (business interests), the Senior User (user interests and benefits) and the Senior Supplier (supplier/technical interests), together representing the three primary stakeholder interests.
Which Project Board member specifies the users' needs and is accountable for ensuring the expected benefits are realised?
- a.The Executive
- b.The Senior Supplier
- c.The Senior User✓
- d.Project Assurance
The Senior User represents those who will use the project's products, specifies their requirements, and is accountable for demonstrating that the intended benefits are actually achieved.
What is the primary responsibility of the Project Manager in PRINCE2?
- a.Authorising each management stage on behalf of the organisation
- b.Owning the business case and securing project funding
- c.Physically building the specialist products themselves
- d.Running the project day to day, on behalf of the Project Board, within agreed tolerances✓
The Project Manager manages the project on a day-to-day basis for the Project Board, planning and controlling the work to deliver products within the tolerances the board has set, escalating exceptions when needed.