20 questions

Lean-Agile Principles & Mindset

SAFe is founded on:

  • a.Waterfall stage gates
  • b.A single project methodology
  • c.Fixed annual project plans
  • d.Lean and Agile principles✓

SAFe is built on Lean-Agile principles and values.

Lean-Agile Principles & Mindset

Which is a SAFe Lean-Agile principle?

  • a.Plan everything once, upfront
  • b.Avoid economic thinking
  • c.Centralize all decisions with executives
  • d.Decentralize decision-making✓

Decentralizing decision-making is a core SAFe principle.

Lean-Agile Principles & Mindset

In the SAFe House of Lean, the goal at the top is:

  • a.Utilization
  • b.Value✓
  • c.Individual bonuses
  • d.Documentation

The goal of the House of Lean is value.

Lean-Agile Principles & Mindset

'Take an economic view' means teams should:

  • a.Understand cost of delay and sequence jobs for best economic outcome✓
  • b.Never sequence work
  • c.Optimize only local team metrics
  • d.Ignore cost of delay

Taking an economic view includes understanding cost of delay to sequence work.

Agile Release Train

The Agile Release Train (ART) is best described as:

  • a.A long-lived team of agile teams delivering value in a value stream✓
  • b.A single agile team
  • c.A one-time project
  • d.A portfolio funding model

An ART is a team of agile teams that continuously delivers value.

Agile Release Train

A typical ART includes roughly how many people?

  • a.5 to 9
  • b.50 to 125✓
  • c.1 to 3
  • d.500 to 1000

An ART is usually 50-125 people (a 'Dunbar number' scale).

Agile Release Train

The fixed timebox on which an ART delivers is called the:

  • a.Release
  • b.Program Increment (PI)✓
  • c.Fiscal year
  • d.Sprint

The Program Increment (PI) is the ART's cadence, usually 8-12 weeks.

Agile Release Train

The ART aligns teams to a common:

  • a.Office location
  • b.Manager
  • c.Mission and cadence✓
  • d.Programming language

Teams on an ART share a mission and operate on a common cadence.

PI Planning

PI Planning is:

  • a.A cadence-based event where all ART teams plan the next PI together✓
  • b.An optional yearly workshop
  • c.A daily standup
  • d.A portfolio budgeting meeting

PI Planning is a regular event aligning all ART teams on the upcoming PI.

PI Planning

A key output of PI Planning is:

  • a.A ten-year roadmap
  • b.A signed fixed-scope contract
  • c.Individual performance reviews
  • d.Committed PI objectives and a program board✓

PI Planning produces committed PI objectives and a program (ART) board.

PI Planning

The program board created in PI Planning primarily visualizes:

  • a.Source code
  • b.Features, milestones, and cross-team dependencies✓
  • c.Office seating
  • d.Team salaries

The program board shows features, milestones, and dependencies across teams.

PI Planning

Business owners assign business value to PI objectives to:

  • a.Set budgets for the year
  • b.Align teams on what matters most to the business✓
  • c.Replace the backlog
  • d.Rank employees

Business value ratings align teams on the most important objectives.

Lean Portfolio Management

Lean Portfolio Management funds:

  • a.Individual projects
  • b.Value streams✓
  • c.Single sprints
  • d.Only executives' initiatives

LPM funds value streams rather than temporary projects.

Lean Portfolio Management

A benefit of funding value streams instead of projects is:

  • a.Reduced overhead and faster, more flexible decisions✓
  • b.More detailed upfront project plans
  • c.Longer approval cycles
  • d.Less alignment to strategy

Lean budgets with guardrails reduce overhead and speed decisions.

Lean Portfolio Management

A portfolio Epic in SAFe is:

  • a.A defect
  • b.A large initiative requiring analysis (a lightweight business case)✓
  • c.A daily task
  • d.A single user story

Epics are large initiatives evaluated with a lightweight business case.

Lean Portfolio Management

Guardrails in Lean budgets exist to:

  • a.Assign work to individuals
  • b.Eliminate all governance
  • c.Remove strategic alignment
  • d.Guide spending and investment within value streams✓

Guardrails govern how value-stream budgets are spent while keeping flexibility.

Leading the Transformation

Lean-Agile leaders are expected to:

  • a.Lead by example and empower teams✓
  • b.Command and control teams
  • c.Avoid learning the framework
  • d.Make every team decision

Lean-Agile leaders model the mindset and empower teams.

Leading the Transformation

A leader practicing 'Lead by example' would:

  • a.Learn and demonstrate Lean-Agile behaviors themselves✓
  • b.Delegate all learning to others
  • c.Rely only on status reports
  • d.Enforce fixed plans rigidly

Leading by example means embodying the Lean-Agile mindset personally.

Leading the Transformation

Empowering teams to make decisions supports the SAFe principle of:

  • a.Maximizing utilization
  • b.Decentralized decision-making✓
  • c.Centralized control
  • d.Fixed annual planning

Empowered teams reflect decentralized decision-making.

Leading the Transformation

Relentless improvement in SAFe is pursued through:

  • a.Blaming individuals
  • b.A one-time training
  • c.Ignoring problems
  • d.Regular Inspect and Adapt events✓

Inspect and Adapt (I&A) drives relentless improvement each PI.