Plumbing Codes: Design and Commercial Systems
The master exam leans toward design: how many fixtures a building needs, how stacks and vents are sized in tall buildings, and how storm drainage, interceptors and pumped systems are laid out. Section numbers are from the 2018 International Plumbing Code. The official exam also includes sizing charts and a multi-story design exercise that this bank does not reproduce.
Fixture counts and water supply
Fixture counts start from the occupant load, split equally between the sexes. Water distribution is sized from water supply fixture units, the pressure available after static head and losses, and the developed length to the most remote fixture.
Stacks, vents and pumped drainage
Stacks are sized by drainage fixture units and height in branch intervals. Tall stacks need vent stacks and relief vents, and fixtures below the sewer are pumped from a covered, vented sump.
Storm drainage and interceptors
Roof drainage is sized on the 100-year, 1-hour rainfall rate. Where a parapet could pond water, a separate secondary system discharges where it will be seen. Grease interceptors are rated by flow and need a flow control.
Tests and administration
An alternative design is submitted by a registered design professional, and alternative materials must be equivalent to what the code prescribes. The rough-in inspection comes before piping is covered.