Texas Master Plumber Exam — All Questions
60 questions
A restaurant has an occupant load of 300. Under IPC §403.1.1, the fixture count is worked out by assuming the occupants are:
- a.40 percent male and 60 percent female
- b.100 percent of each sex, counted twice
- c.60 percent male and 40 percent female
- d.50 percent male and 50 percent female✓
Unless statistical data approved by the code official shows otherwise, the occupant load is divided half and half before the fixture ratios in Table 403.1 are applied to each sex.IPC §403.1.1
Under IPC §403.2, separate toilet facilities for each sex are NOT required in a structure or tenant space with a total occupant load, including employees and customers, of:
- a.50 or fewer
- b.75 or fewer
- c.150 or fewer
- d.15 or fewer✓
Separate facilities are not required for dwelling units and sleeping units, for spaces with a total occupant load of 15 or fewer, or for mercantile occupancies of 100 or fewer. Larger spaces need facilities for each sex.IPC §403.2
In a covered mall, IPC §403.3.4 limits the path of travel from a tenant space to the required public toilet facilities to:
- a.1,000 feet
- b.100 feet
- c.750 feet
- d.300 feet✓
In covered and open mall buildings the travel distance, measured from the main entrance of any store or tenant space, may not exceed 300 feet. Other occupancies use 500 feet.IPC §403.3.4
Under IPC §410.4, where approved water dispensers are provided in an office building, they may substitute for:
- a.Not more than 10 percent of the required drinking fountains
- b.None, because substitution is not allowed in any occupancy
- c.All of the required drinking fountains in every occupancy
- d.Not more than 50 percent of the required drinking fountains✓
Restaurants that provide drinking water free of charge need no fountains, and in other occupancies water dispensers may replace up to 50 percent of the required fountains.IPC §410.4
Under IPC §606.2, a shutoff valve is required on the fixture supply to each plumbing fixture EXCEPT:
- a.Lavatories in commercial and public buildings
- b.Kitchen sinks in apartment buildings of any height or age
- c.Bathtubs and showers in one- and two-family dwellings✓
- d.Water closets in one- and two-family dwellings
Shutoff valves are required on the supply to each fixture other than bathtubs and showers in one- and two-family dwellings and in hotel guest rooms that have unit shutoffs.IPC §606.2
A water distribution system is being sized. The water supply fixture unit is best described as:
- a.A measure of the probable demand a fixture places on the supply✓
- b.The pressure, in psi, required at the outlet of a fixture
- c.The volume, in gallons, a fixture uses in a single operation
- d.The actual flow, in gallons per minute, of a fixture's faucet or valve
A water supply fixture unit expresses the probable hydraulic demand of a fixture, allowing for the chance that not all fixtures run at once. Totals are converted to gpm with a demand curve or table.IPC §202; IPC Appendix E
When sizing a water system by the IPC Appendix E method, the pressure available for friction loss is found by taking the minimum street pressure and subtracting:
- a.Static head loss, the pressure needed at the highest fixture and meter and device losses✓
- b.Only the friction loss in the water service between the main and the meter
- c.The pressure rating stamped on the pipe that is used for the water service
- d.Only the pressure needed at the fixture that is nearest the water meter
Available friction pressure equals the minimum supply pressure less the elevation loss, the required residual at the most demanding outlet and losses through meters, backflow preventers and other devices. What remains is spread over the developed length.IPC Appendix E
The developed length of the piping to the most remote fixture is 200 feet, and 20 psi is available for friction loss. The allowable friction loss per 100 feet is:
- a.20 psi per 100 feet
- b.40 psi per 100 feet
- c.10 psi per 100 feet✓
- d.4 psi per 100 feet
Loss per 100 feet = available pressure × 100 ÷ developed length = 20 × 100 ÷ 200 = 10 psi. Designers usually increase the length for fittings before dividing.IPC Appendix E
Under IPC §604.3, the minimum flow pressure required at a flushometer valve water closet (siphonic, other than blowout type) is generally higher than at a lavatory faucet because:
- a.The valve must pass a high flow rate in a few seconds to flush the bowl✓
- b.The supply pipe to a flushometer is smaller than a lavatory supply
- c.The valve contains a vacuum breaker that must be kept shut by water pressure
- d.The fixture is always installed on the top floor of a building
Flushometer valves need a high instantaneous flow, so the table of required capacities at fixture outlets lists higher flow pressures for them than for faucets. The vacuum breaker and location are not the reason.IPC §604.3
Under IPC §607.2, the developed length of hot water piping from the source of hot water to a fixture may not exceed:
- a.300 feet
- b.10 feet
- c.50 feet✓
- d.150 feet
The maximum developed length from the source (a heater, a recirculating loop or heat-traced pipe) to the fixture is 50 feet, which limits the water wasted while waiting for hot water.IPC §607.2
Under IPC §501.2, a water heater that supplies both potable hot water and space heating at temperatures above 140°F must have:
- a.A reduced pressure backflow assembly on its outlet
- b.A master thermostatic mixing valve conforming to ASSE 1017✓
- c.A pressure-reducing valve set to 25 psi on its inlet
- d.A second relief valve conforming to ASME Section VIII
Where a combination system heats water above 140°F for space heating, a tempering valve complying with ASSE 1017 limits the water sent to the potable distribution system to 140°F or less.IPC §501.2
"Tempered water" for public hand-washing facilities is defined in the IPC as water between:
- a.60°F and 80°F
- b.110°F and 140°F
- c.85°F and 110°F✓
- d.140°F and 180°F
Tempered water has a temperature range of 85°F to 110°F and is delivered to public hand-washing fixtures through an approved temperature-limiting device.IPC §§202, 607.1.2
Under IPC §604.9, a water hammer arrestor installed where quick-closing valves are used must conform to:
- a.ASSE 1013
- b.ASSE 1070
- c.ASSE 1016
- d.ASSE 1010✓
Water hammer arrestors conform to ASSE 1010 and are installed per the manufacturer's instructions. ASSE 1016 covers shower valves, 1070 temperature limiters and 1013 reduced pressure assemblies.IPC §604.9
A commercial building's fire sprinkler system has an antifreeze loop. Under IPC §608.16.4.1, the potable supply must be protected by:
- a.A double check valve assembly without test cocks
- b.A reduced pressure principle backflow prevention assembly✓
- c.A single swing check valve on the fire service
- d.An atmospheric vacuum breaker above the riser
Where a fire protection system contains chemical additives or antifreeze, a reduced pressure principle assembly is required. A double check assembly is accepted only where no additives are used.IPC §608.16.4.1
Under IPC §608.17.4, the potable water supply to an automatic sprinkler system that has a fire department connection must be protected by at least:
- a.A double check backflow prevention assembly✓
- b.An air gap at the fire department connection
- c.No protection, since the water is potable
- d.A hose connection vacuum breaker on the riser
The potable supply to automatic sprinkler and standpipe systems is protected by a double check backflow prevention assembly, a double check fire protection backflow prevention assembly or a reduced pressure principle fire protection backflow prevention assembly. Only systems installed as part of the water distribution system with no fire department connection are exempt.IPC §608.17.4
A carbonated beverage dispenser is connected to the water supply. Under IPC §608.16.1, the supply is protected by a backflow preventer conforming to ASSE 1022 or an air gap, and the piping downstream of the device may not be:
- a.Stainless steel
- b.Polyethylene tubing
- c.Copper✓
- d.Braided food-grade hose
Carbonated water is acidic and leaches copper, so the piping from the backflow preventer to the carbonator is not affected by carbon dioxide; copper is excluded. Stainless steel and listed plastics are used.IPC §608.16.1
Under IPC §608.8, non-potable water piping in a building with a dual water system must be identified:
- a.By a note on the drawings only, because field marking fades with time
- b.By painting the pipe hangers yellow wherever the pipe is exposed to view in a mechanical room or shaft
- c.By colour marking, metal tags or tape at intervals of 25 feet or less and at each floor or wall penetration✓
- d.By a single label at the water meter that lists every non-potable outlet in the building by room number
Where non-potable systems are installed, the piping is identified by colour marking or tags at intervals not exceeding 25 feet and at each point where it passes through a wall, floor or roof. Reclaimed water piping is purple.IPC §608.8
A drainage stack is 3 inches in diameter. Under IPC §710.1, the size of a stack is based on:
- a.The total drainage fixture units connected and the stack height in branch intervals✓
- b.The total developed length of all horizontal branches that connect to it
- c.The diameter of the building sewer at the point where it leaves the lot
- d.The number of water closets connected, whatever the other fixtures may be
Stack size comes from the table of horizontal fixture branches and stacks, entered with the total fixture units, the load per branch interval and whether the stack is more than three branch intervals high.IPC §710.1
A "branch interval", as used for sizing stacks in the IPC, is a vertical length of stack of at least:
- a.2 feet, within which the horizontal branches from one floor connect
- b.8 feet, within which the horizontal branches from one floor connect✓
- c.20 feet, within which the branches from two floors connect
- d.40 feet, within which the branches from four floors connect
A branch interval is a vertical measurement of distance, 8 feet or more in developed length, between the connections of horizontal branches to a stack; it usually corresponds to a story.IPC §202
Under IPC §711.1, a horizontal branch may not connect to the building drain or a horizontal offset within what distance downstream of a stack?
- a.50 times the diameter of the drainage stack
- b.10 times the diameter of the drainage stack✓
- c.100 times the diameter of the drainage stack
- d.2 times the diameter of the drainage stack
Hydraulic jump at the base of a stack creates pressure, so horizontal branches connect at least 10 stack diameters downstream of the stack. Closer connections risk blown trap seals.IPC §711.1
Under IPC §904.2, a vent stack is required for a drainage stack that has:
- a.Twenty or more branch intervals
- b.Five or more branch intervals✓
- c.Two or more branch intervals
- d.Ten or more branch intervals
A vent stack is required for every drainage stack of five branch intervals or more, except stacks designed as waste stack vents or served by other approved systems.IPC §904.2
Under IPC §908.1, a soil or waste stack in a building of more than 10 branch intervals needs a relief vent at:
- a.Each second interval, counting from the lowest floor
- b.The top interval only, just below the roof
- c.The lowest interval only, just above the base
- d.Each tenth interval, counting from the top floor✓
Stacks of more than 10 branch intervals have a relief vent at each tenth interval installed, beginning with the top floor, to equalise pressure between the drainage stack and the vent stack.IPC §908.1
Under IPC §904.4, a vent stack must connect to the drainage stack:
- a.At or below the lowest horizontal branch✓
- b.At the midpoint of the drainage stack
- c.At the roof, through the vent terminal
- d.Above the highest horizontal branch only
Every vent stack connects to the base of the drainage stack, at or below the lowest horizontal branch, or to the building drain within 10 stack diameters downstream, so that pressure at the base is relieved.IPC §904.4
A sewage ejector sump is vented. Under IPC §906.5.1, the sump vent for a sewage pump or ejector other than a pneumatic ejector may not be smaller than:
- a.3/4 inch
- b.4 inches
- c.1-1/4 inches✓
- d.2-1/2 inches
Sump vents are sized by the pump discharge rate and vent length, with a minimum of 1-1/4 inches. Pneumatic ejectors need a separate relief vent of at least 1-1/4 inches run independently to outdoors.IPC §906.5
Under IPC §712.3.5, the discharge pipe from a sewage ejector must connect to the gravity drain through:
- a.A saddle fitting, strapped over a hole cut in the drain
- b.A double sanitary tee shared with a nearby fixture drain
- c.A sanitary tee, entering on its side at the centreline of the pipe
- d.A wye fitting, entering from the top of the horizontal drain✓
Pumped discharge enters a horizontal drain from the top through a wye, at least 10 pipe diameters from the base of any stack, so the pumped flow does not back up into gravity branches.IPC §712.3.5
Under IPC §712.4.2, a sewage ejector that receives the discharge of water closets must be able to pass solids of at least:
- a.2 inches in diameter, unless it is a grinder pump✓
- b.6 inches in diameter, in every installation
- c.4 inches in diameter, unless it is a grinder pump
- d.1/4 inch in diameter, in every installation
Sewage pumps and ejectors receiving water closet waste handle spherical solids up to 2 inches and have a discharge of at least 2 inches; grinder pumps and grinder ejectors may use a 1-1/4-inch discharge.IPC §712.4.2
A building has fixtures on a floor below the level of the public sewer. Under IPC §712.1, the waste from those fixtures must:
- a.Flow to a dry well under the floor slab of the lowest level
- b.Discharge to a tightly covered, vented sump and be pumped to the gravity drain✓
- c.Flow by gravity through a backwater valve into the public sewer
- d.Discharge to an open floor sump that is emptied by hand each week
Building subdrains that cannot discharge by gravity go to a sealed and vented sump, from which the contents are lifted by an automatic pump or ejector. A backwater valve cannot make water run uphill.IPC §712.1
Storm drainage for a roof is sized, under IPC §1106.1, on the basis of:
- a.The 2-year, 24-hour rainfall total for the location
- b.The heaviest rainfall of the previous year
- c.The average annual rainfall for the county
- d.The 100-year, 1-hour rainfall rate for the location✓
Vertical conductors, leaders, building storm drains and sewers are sized for the 100-year hourly rainfall rate, taken from the code's maps or approved local weather data.IPC §1106.1
A storm water sump pit is installed for a building subdrain. Under IPC §1113.1.2, the pit must be at least:
- a.60 inches in diameter and 96 inches deep
- b.36 inches in diameter and 72 inches deep
- c.6 inches in diameter and 12 inches deep
- d.18 inches in diameter and 24 inches deep✓
A storm sump pit is not less than 18 inches in diameter and 24 inches deep, accessible, with a removable cover that can carry the expected loads. A smaller pit short-cycles the pump.IPC §1113.1.2
Where a parapet would trap water if the primary roof drains were blocked, IPC §1108.1 requires:
- a.A larger vent stack through the roof
- b.A sump pump installed on the roof surface
- c.Secondary (emergency) roof drains or scuppers✓
- d.A second layer of roofing membrane over the deck
Where roof perimeter construction extends above the roof so that water would be entrapped if the primary drains allowed build-up, secondary drains or scuppers are required.IPC §1108.1
Under IPC §1108.2, a secondary roof drain system must discharge:
- a.Through separate piping to a point above grade where occupants would normally see it✓
- b.Into the vent stack that is nearest to the secondary roof drain
- c.Into the primary storm conductor just below the level of the roof deck
- d.Into the sanitary building drain through a trap and a backwater valve
Secondary drains have separate piping and discharge above grade in a location normally observed by occupants or maintenance staff, so flow from them signals that the primary system is blocked.IPC §1108.2
Under IPC §1101.3, storm water may NOT be drained into:
- a.A storm sewer under the public street
- b.A sewer intended for sanitary sewage only✓
- c.An approved point of disposal on the lot
- d.A combined sewer approved by the authority
Storm water does not discharge into sanitary-only sewers, because the peak flow overloads the sewer and treatment plant. Combined sewers, storm sewers and approved disposal points are permitted.IPC §1101.3
Under IPC §1104.1, a rainwater conductor or leader may not be used as:
- a.A soil, waste or vent pipe✓
- b.A drain for a balcony or deck
- c.A storm drain for an adjoining roof
- d.A drain for a parking canopy
Conductors and leaders carry storm water only; they are not used as soil, waste or vent pipes, and soil, waste and vent pipes are not used as conductors.IPC §1104.1
A subsoil (foundation) drain is installed around a basement. Under IPC §1111.1, the pipe must be at least:
- a.8 inches in diameter
- b.12 inches in diameter
- c.4 inches in diameter✓
- d.1 inch in diameter
Subsoil drains are open-jointed, horizontally split or perforated pipe not less than 4 inches in diameter, discharging to a sump or approved location; a backwater valve protects a gravity connection.IPC §1111.1
Under IPC §1202.1, non-flammable medical gas systems in a hospital are designed and installed in accordance with:
- a.NFPA 58
- b.NFPA 13D
- c.NFPA 99✓
- d.NFPA 211
Medical gas and vacuum systems follow NFPA 99, Health Care Facilities Code. NFPA 13D covers residential sprinklers, NFPA 58 LP-gas and NFPA 211 chimneys.IPC §1202.1
Under IPC §802.1.3, a sterilizer that discharges potable water to the building drainage system must be:
- a.Directly connected, with a backwater valve at the outlet
- b.Indirectly connected, with the discharge heated to 180°F or more
- c.Directly connected, with a deep-seal trap of 6 inches or more
- d.Indirectly connected, with the discharge made through an air gap✓
Devices such as sterilizers and relief valves that discharge potable water to the drainage system do so through an indirect waste pipe by means of an air gap, so sewage cannot back up into the equipment.IPC §802.1.3
Under IPC §1003.3.4, hydromechanical grease interceptors are sized and rated according to:
- a.The number of meals served per day, under the water utility's rate schedule
- b.The diameter of the building sewer, under the sizing table for horizontal drains
- c.The number of seats in the dining room, under the state health department rules
- d.Their flow rate in gallons per minute, under standards such as PDI G101 or ASME A112.14.3✓
Hydromechanical units are tested and rated by flow rate and grease retention under PDI G101, ASME A112.14.3 or A112.14.4, and are fitted with a flow control device. Gravity interceptors are sized by volume instead.IPC §1003.3.4
A hydromechanical grease interceptor is installed with a vented flow control. Under IPC §1003.3.4.2, the flow control device:
- a.Grinds food solids so that they pass through the interceptor to the sewer
- b.Mixes hot water with the waste so that grease stays liquid through the unit
- c.Limits the rate of flow so that it does not exceed the interceptor's rated capacity✓
- d.Opens a bypass around the interceptor whenever the kitchen flow is heavy
The flow control restricts flow to the rated gpm and introduces air so grease separates; it is vented and never used as a bypass. Heat and grinding both carry grease through the unit.IPC §1003.3.4.2
Under IPC §1003.9, interceptors and separators must be designed so they do not become air bound, and they are vented:
- a.Only where installed outdoors below grade
- b.By one of the venting methods in Chapter 9✓
- c.Only where made of fibreglass or plastic
- d.Only where they hold more than 50 gallons
Interceptors and separators are designed so they do not become air bound and are vented in accordance with one of the methods in Chapter 9. Material, volume and location are not the test.IPC §1003.9
Under IPC §1003.10, each interceptor and separator must be installed so that:
- a.It drains directly into the storm sewer rather than the sanitary sewer
- b.It is fully buried under the kitchen floor slab with no cover above grade
- c.It is accessible for inspection, cleaning and removal of the intercepted material✓
- d.It can be bypassed during the hours when the building is fully occupied
Access for servicing is required; an interceptor that cannot be opened is never cleaned and soon passes grease or oil to the sewer. Bypasses and storm connections are not permitted.IPC §1003.10
A commercial dishwashing machine is connected to the drainage system. Under IPC §802.1.6, it must discharge:
- a.Directly, through a running trap on the building drain
- b.Indirectly, through a hose laid in a floor drain body
- c.Indirectly, through an air gap or air break into a waste receptor✓
- d.Directly, through the vent of the nearest sink
Commercial dishwashing machines discharge indirectly through an air gap or air break into a standpipe or waste receptor. A hose pushed into a floor drain gives no air break.IPC §802.1.6
Under IPC §802.1.1, a floor drain located inside a walk-in refrigerator or freezer where food is stored must be:
- a.Directly connected to the storm drainage system by a deep-seal trap
- b.Indirectly connected to the sanitary drainage system by an air gap✓
- c.Directly connected to the grease interceptor inlet
- d.Sealed with a threaded plug at all times
Floor drains in walk-in coolers and food storage areas are indirectly connected by an air gap; an exception allows an air break where a backwater valve protects the drain in some cases.IPC §802.1.1
Under IPC §706.3, a double sanitary tee may NOT receive the discharge of:
- a.Back-to-back water closets or fixtures with pumping action discharge✓
- b.Two bathtubs located on opposite sides of a common wall
- c.Two drinking fountains located on opposite sides of a wall
- d.Back-to-back lavatories that are served by a common vent
Double sanitary tee patterns do not receive back-to-back water closets or appliances with pumping action, because the discharge can cross the fitting into the opposite branch; a double wye or combination pattern is used, subject to a limited exception.IPC §706.3
An engineer proposes a single-stack drainage design that departs from the prescriptive tables. Under IPC §316, the code official may accept it where:
- a.The building owner agrees in writing to maintain the system for ten years
- b.The pipe manufacturer provides a brochure describing similar installations
- c.The Responsible Master Plumber signs a letter accepting liability for the system
- d.A registered design professional submits documents showing it meets the intent of the code✓
An alternative engineered design is submitted by a registered design professional with drawings and calculations, and must conform to the intent of the code with equivalent performance. Letters and brochures are not enough.IPC §316
Under IPC §105.2, a material or method not specifically described in the code may be approved by the code official where it:
- a.Costs less than the material or method that the code describes for the same work, and is quicker to install
- b.Has been used on at least three other projects in the same municipality
- c.Is recommended by the wholesaler who supplies the plumbing contractor
- d.Complies with the intent of the code and is at least equivalent in quality, strength and safety✓
Alternative materials, methods and equipment are approved where the code official finds them satisfactory, compliant with the code's intent and not less than equivalent in quality, strength, effectiveness, fire resistance, durability and safety.IPC §105.2
Under IPC §107.2, which inspection is made after the piping is installed but before it is covered?
- a.The final inspection
- b.The annual inspection
- c.The rough-in inspection✓
- d.The underground inspection
Underground inspection is made after trenches are dug and piping laid, before backfill; rough-in inspection after roof, framing and rough piping are in place and before wall or ceiling membranes; final inspection after the work is complete.IPC §107.2
Under IPC §708.1.4, a cleanout is required at each change of direction of the building drain greater than 45 degrees, except that only one cleanout is needed for each:
- a.5 feet of developed length where there are multiple changes
- b.200 feet of developed length where there are multiple changes
- c.40 feet of developed length where there are multiple changes✓
- d.500 feet of developed length where there are multiple changes
Where more than one change of direction greater than 45 degrees occurs in a run, only one cleanout is required for each 40 feet of developed length of the drain.IPC §708.1.4
Under IPC §708.1.5, a cleanout serving an 8-inch building sewer must be at least:
- a.3 inches in size
- b.1 inch in size
- c.2 inches in size
- d.4 inches in size✓
Cleanouts are the same size as the piping served, except that cleanouts for piping larger than 4 inches need not be larger than 4 inches. Smaller openings will not pass cleaning equipment.IPC §708.1.5
Under IPC §708.1.2, a building sewer 8 inches or larger must have a manhole located not more than what distance from the junction of the building drain and the building sewer?
- a.500 feet
- b.200 feet✓
- c.1,000 feet
- d.50 feet
Building sewers 8 inches and larger have a manhole not more than 200 feet from the junction of the building drain and building sewer, and at intervals of not more than 400 feet after that. Smaller building sewers have cleanouts at intervals of not more than 100 feet.IPC §708.1.2
Under IPC §714.1, plumbing fixtures on a floor ABOVE the elevation of the next upstream manhole cover:
- a.Must discharge through a sewage ejector
- b.Must discharge through a backwater valve too
- c.May not discharge through a backwater valve✓
- d.May not connect to the public sewer at all
Only fixtures with flood rims below the next upstream manhole cover discharge through the backwater valve. Routing upper-floor fixtures through it would flood the lower level when the valve closes.IPC §714.1