Plumbing License Law and Board Rules

Under Occupations Code §1301.002, a journeyman plumber with no apprenticeship programme behind them qualifies to sit for the master plumber exam after working as a journeyman for at least:

  • a.Eight years
  • b.Two years✓
  • c.Six months
  • d.Four years

The statute defines a master plumber as someone who has worked as a journeyman for at least two years, or for at least one year after completing a training programme approved by the U.S. Department of Labor Office of Apprenticeship or another nationally recognised programme accepted by the Board.Tex. Occ. Code §1301.002

Plumbing License Law and Board Rules

A journeyman completed a U.S. Department of Labor approved apprenticeship programme. Under §1301.002, the journeyman experience needed for the master exam drops to at least:

  • a.One year✓
  • b.Thirty days
  • c.Five years
  • d.Three years

Completing a Department of Labor approved or other nationally recognised apprenticeship programme accepted by the Board cuts the journeyman period from two years to one. The other periods are not in the statute.Tex. Occ. Code §1301.002

Plumbing License Law and Board Rules

Before a master plumber starts working as a Responsible Master Plumber, §1301.3576 requires the master to give the Board:

  • a.A certificate of insurance that meets §1301.552✓
  • b.A surety bond in the amount of $25,000
  • c.A list of every apprentice the company will employ
  • d.A copy of the company's municipal permits to date

A master plumber must provide the Board with a certificate of insurance meeting §1301.552 before acting as a Responsible Master Plumber. The statute does not ask for a bond, an apprentice list or permit copies at that step.Tex. Occ. Code §1301.3576

Plumbing License Law and Board Rules

The commercial general liability insurance a Responsible Master Plumber must carry under §1301.552 is at least:

  • a.$1,000,000 for all claims arising in a two-year period
  • b.$500,000 for each claim, with no annual limit stated
  • c.$300,000 for all claims arising in a one-year period✓
  • d.$100,000 for all claims arising in a one-year period

The certificate of insurance must show coverage of not less than $300,000 for all claims arising in any one-year period. The other figures are not the statutory amount.Tex. Occ. Code §1301.552

Plumbing License Law and Board Rules

A master plumber is asked to be the Responsible Master Plumber for a second, unrelated plumbing company at the same time. Under 22 TAC §367.5, the master:

  • a.May, so long as both companies are located in the same municipality
  • b.May not, because an RMP may act for only one plumbing company at a time✓
  • c.May not, unless the Board is paid a second annual license fee
  • d.May, so long as each company employs at least one journeyman plumber full time

A master plumber may serve as the Responsible Master Plumber for only one plumbing company at a time. Location, staffing and extra fees do not create an exception.22 TAC §367.5

Plumbing License Law and Board Rules

A Responsible Master Plumber leaves a plumbing company. Under 22 TAC §367.5, the Board must be notified in writing within:

  • a.24 hours
  • b.90 calendar days
  • c.10 business days✓
  • d.60 calendar days

A change in the Responsible Master Plumber relationship is reported to the Board within 10 business days. The company cannot offer plumbing to the public without an RMP in place.22 TAC §367.5

Plumbing License Law and Board Rules

A company that only employs journeyman plumbers runs online advertisements offering plumbing repairs. Under §1301.351(a-2), the company must first:

  • a.Obtain a plumbing inspector's written approval
  • b.Register each advertisement with the city secretary
  • c.Post a bond with the county clerk's office
  • d.Secure the services of a Responsible Master Plumber✓

A person who advertises or otherwise offers to perform plumbing must secure the services of a Responsible Master Plumber. Advertising is not registered with cities, approved by inspectors or bonded with the county.Tex. Occ. Code §1301.351(a-2); 22 TAC §367.9

Plumbing License Law and Board Rules

Under §1301.351(d), a licensed plumber on a job site must have the license:

  • a.Attached to the permit card at the job entrance
  • b.Posted on the dashboard of the service vehicle
  • c.On file at the company office during business hours
  • d.On his or her person while engaged in plumbing✓

A holder of a license or registration carries it on his or her person while engaged in plumbing, so an inspector or Board investigator can check it. A copy at the office or in the truck does not meet the rule.Tex. Occ. Code §1301.351(d)

Plumbing License Law and Board Rules

A master plumber supervises new one-family houses in an unincorporated area. Under §1301.351(c), the supervising license holder must:

  • a.Have training and management responsibility for the work and review and inspect it✓
  • b.Visit the site only if the owner files a written complaint with the Board
  • c.Hire a municipal plumbing inspector to approve each stage of the work
  • d.Remain on the site continuously whenever any registered apprentice is working

For new one- and two-family dwellings in unincorporated areas, the supervising licensee has training and management responsibility and reviews and inspects the work, but continuous on-the-job oversight is not required.Tex. Occ. Code §1301.351(c)

Plumbing License Law and Board Rules

Who may install piping used solely to carry gas or vacuum for medical purposes under §1301.356?

  • a.Any master plumber, because the master license includes all endorsements
  • b.A master or journeyman plumber who holds the medical gas piping installation endorsement✓
  • c.A tradesman plumber-limited who works under a master plumber's direct supervision
  • d.A registered apprentice who has passed a brazing test given by the employer

Medical gas and medical vacuum piping may be installed only by a licensed master or journeyman who also holds the endorsement, earned by a separate examination. The master license alone is not enough.Tex. Occ. Code §1301.356

Plumbing License Law and Board Rules

Under §1301.452, which act is a ground for disciplinary action by the Board?

  • a.Using a plumbing code that the Board has adopted by rule
  • b.Declining to bid on a job that the plumber considers too small or unprofitable
  • c.Charging a higher hourly rate than other plumbing companies in the city
  • d.Making a false promise intended to induce a person to contract for a service✓

Grounds include fraud in obtaining a license, violating municipal plumbing ordinances, misrepresenting services, false promises to induce a contract, and employing unlicensed persons. Pricing and declining work are business decisions.Tex. Occ. Code §1301.452

Plumbing License Law and Board Rules

A plumbing company puts an unregistered helper to work installing water lines. Under §§1301.452 and 1301.508, the employer:

  • a.Is subject to discipline and commits a Class C misdemeanor✓
  • b.Is subject only to a warning letter for a first violation of this kind
  • c.Has no liability, because only the helper is in violation
  • d.Commits a felony punishable by confinement in state jail

Employing a person who lacks the required license, endorsement or registration is both a ground for discipline and an offense, which is a Class C misdemeanor. It is not a felony, and the employer is not excused.Tex. Occ. Code §§1301.452, 1301.508

Plumbing License Law and Board Rules

When the Board suspects a licensee is incompetent, §1301.452(b) lets the Board use what tool to decide whether grounds for suspension exist?

  • a.A credit report
  • b.Retesting procedures✓
  • c.A customer survey
  • d.A polygraph test

Retesting procedures may be used to determine whether grounds exist for suspension or revocation due to incompetence or a wilful violation. The other tools are not in the statute.Tex. Occ. Code §1301.452(b)

Plumbing License Law and Board Rules

Under §1301.502, who may issue a citation to a person for a violation described in §1301.508?

  • a.Any Responsible Master Plumber who witnesses the violation on a job site
  • b.Only a peace officer commissioned by the Texas Department of Public Safety
  • c.A municipal plumbing inspector within the municipality, or a water district plumbing inspector✓
  • d.Any licensed journeyman plumber employed by a competing plumbing company

Citations may be issued by a water district plumbing inspector or, within the jurisdiction of the municipality, a municipal plumbing inspector. Licensed plumbers have no citation power.Tex. Occ. Code §1301.502

Plumbing License Law and Board Rules

The maximum administrative penalty the Board may impose under §1301.702 is:

  • a.$5,000 in total, however many days the violation continues
  • b.$50,000 per violation, with no account taken of how long it lasted
  • c.$5,000 per violation, with each day counted as a separate violation✓
  • d.$500 per violation, with each day counted as a separate violation

The penalty may not exceed $5,000 for each violation, and each day a violation continues or occurs is a separate violation. The amount is set using factors such as seriousness, harm, history and deterrence.Tex. Occ. Code §1301.702

Plumbing License Law and Board Rules

Which factor does §1301.702 direct the Board to weigh when setting the amount of an administrative penalty?

  • a.The length of time the license has been held
  • b.The city in which the company has its office
  • c.The number of trucks the company operates
  • d.The history of previous violations✓

The amount is based on the seriousness of the violation, economic harm, history of previous violations, the amount needed to deter future violations, efforts to correct the violation and other matters justice requires.Tex. Occ. Code §1301.702(b)

Plumbing License Law and Board Rules

After an informal settlement conference, the Board orders a plumber to pay restitution to a customer. Under §1301.5071, the restitution may not exceed:

  • a.Three times the amount the customer paid for the regulated service
  • b.The customer's estimated total losses, including consequential damages
  • c.The policy limit of the plumber's general liability insurance
  • d.The amount the customer paid the plumber for the regulated service✓

Restitution ordered through an informal settlement is capped at what the person paid the license holder for the service. The Board may not order other damages or estimate harm.Tex. Occ. Code §1301.5071

Plumbing License Law and Board Rules

The Board sues to enjoin an unlicensed person from doing plumbing. Under §1301.504, venue for the action is in:

  • a.The municipal court where the work was done
  • b.A district court in Travis County✓
  • c.A federal district court in Houston
  • d.A justice court in the defendant's precinct

The Board may bring an injunction action in its own name, with venue in a district court in Travis County, and it need not prove that no adequate legal remedy exists.Tex. Occ. Code §1301.504

Plumbing License Law and Board Rules

Which plumbing codes does §1301.255 direct the Board to adopt?

  • a.The National Standard Plumbing Code and the Southern Building Code
  • b.The Uniform Plumbing Code and the International Plumbing Code✓
  • c.The Uniform Plumbing Code only, with no other plumbing code
  • d.The International Plumbing Code only, with no other plumbing code

The Board adopts both the Uniform Plumbing Code and the International Plumbing Code and may adopt later editions by rule; the current rule adopts the 2018 editions. A city chooses which adopted code to enforce.Tex. Occ. Code §1301.255; 22 TAC §367.2

Plumbing License Law and Board Rules

A city adopts one of the Board's plumbing codes. Under §1301.255(d), the city may amend the code:

  • a.To conform to local concerns that do not substantially vary from Board or state rules✓
  • b.Only with the prior written approval of the International Code Council
  • c.Only after every licensed plumber in the city has voted on the change
  • d.In any way it chooses, including removing the requirement for inspections

A municipality or public water system owner may amend code provisions to conform to local concerns, so long as the amendments do not substantially vary from Board rules or other state rules.Tex. Occ. Code §1301.255(d)

Plumbing License Law and Board Rules

Under §1301.255(e), plumbing installed under an adopted code must be inspected by a plumbing inspector who is paid:

  • a.Directly by the general contractor
  • b.Directly by the plumbing contractor's insurer
  • c.Directly by the political subdivision✓
  • d.Directly by the property owner

The political subdivision may contract with any plumbing inspector or qualified inspection business, but the inspector is paid directly by the political subdivision, which keeps the inspector independent of the installer.Tex. Occ. Code §1301.255(e)

Plumbing License Law and Board Rules

Which municipalities MUST regulate plumbing by ordinance under §1301.551?

  • a.Those with more than 500 inhabitants
  • b.Those with more than 5,000 inhabitants✓
  • c.Those that operate a gas utility system
  • d.Those with more than 50,000 inhabitants

A municipality with more than 5,000 inhabitants shall regulate plumbing by ordinance or bylaw; smaller municipalities may do so. The duty does not depend on owning a utility.Tex. Occ. Code §1301.551

Plumbing License Law and Board Rules

Under §1301.551, a city permit is NOT required for which job?

  • a.Replacing a building sewer
  • b.Replacing a water heater
  • c.Extending a gas line
  • d.Replacing a water closet✓

No permit is needed to repair leaks or replace lavatory or kitchen faucets, ballcocks, garbage disposals or water closets. Water heaters, sewers and gas piping need permits.Tex. Occ. Code §1301.551

Plumbing License Law and Board Rules

How many hours of continuing professional education must a master plumber complete each year to renew, under §1301.404?

  • a.24 hours, including 8 on business law, estimating and project management
  • b.2 hours, including 1 on health protection, energy conservation and water conservation
  • c.12 hours, including 6 on business law, estimating and project management
  • d.6 hours, including 3 on health protection, energy conservation and water conservation✓

License holders complete six hours of continuing professional education each year, and three of the six cover health protection, energy conservation and water conservation.Tex. Occ. Code §1301.404

Plumbing License Law and Board Rules

A master license expired 60 days ago. Under §1301.403, the plumber may renew by paying:

  • a.Three times the normal renewal fee
  • b.The normal renewal fee with no added charge of any kind
  • c.One and one-half times the normal renewal fee✓
  • d.Ten times the normal renewal fee

A license expired for 90 days or less renews at one and a half times the normal fee; more than 90 days but less than two years costs twice the fee. After two years the license cannot be renewed.Tex. Occ. Code §1301.403

Plumbing License Law and Board Rules

A master license has been expired for two and a half years. Under §1301.403, to be licensed again the plumber must:

  • a.Pay twice the renewal fee for each year that was missed
  • b.Complete 12 hours of continuing education and pay one fee
  • c.Work for one year as a journeyman under another master
  • d.Meet the requirements for a new license, including examination✓

A license expired for two years or more may not be renewed; the person must comply with the requirements and procedures, including examination, for an original license.Tex. Occ. Code §1301.403

Plumbing License Law and Board Rules

Under 22 TAC §367.3, when a plumbing job is finished the company must give the customer:

  • a.An invoice, only where the charge is more than $500
  • b.A copy of the Responsible Master Plumber's insurance policy
  • c.A copy of the plumber's most recent education certificate
  • d.An invoice, even where no fee is charged for the work✓

On completion the customer receives an invoice, even if no charge is made, showing the company and license information and the Board's contact notice. There is no dollar threshold.22 TAC §367.3

Plumbing License Law and Board Rules

Plumbing company vehicles must display the company name and RMP license number, under the Board's rules:

  • a.On one side, in letters of whatever size is chosen
  • b.On the windshield, in letters at least 1 inch high
  • c.On both sides, in letters at least 2 inches high✓
  • d.On the rear only, in letters at least 6 inches high

Service vehicles show the company name and the Responsible Master Plumber's license number on both sides in characters at least 2 inches high in a contrasting colour.22 TAC §367.10

Plumbing License Law and Board Rules

A customer asks, in writing, for information about a plumbing company's insurance. Under 22 TAC §367.6, the Responsible Master Plumber must supply it within:

  • a.24 hours
  • b.6 months
  • c.1 year
  • d.30 days✓

On written request the Responsible Master Plumber provides insurance information within 30 days. The policy must also cover the specialised work the company performs.22 TAC §367.6

Plumbing License Law and Board Rules

The Board mails a notice of alleged violation to a master plumber. Under 22 TAC §367.17, the plumber must respond within:

  • a.20 days of receiving the notice✓
  • b.3 days of receiving the notice
  • c.90 days of receiving the notice
  • d.180 days of receiving the notice

A person has 20 days after receiving the notice to accept the penalty or request a hearing; a mailed notice is presumed received three days after mailing. Failing to respond leads to a default order.22 TAC §367.17; Tex. Occ. Code §1301.704

Plumbing License Law and Board Rules

A master plumber moves the company office. Under 22 TAC §365.8, the Board must be told of the new address within:

  • a.30 days✓
  • b.120 days
  • c.1 day
  • d.365 days

Licensees and registrants notify the Board of a change of name or address within 30 days, so that renewal and enforcement notices reach them.22 TAC §365.8

Plumbing License Law and Board Rules

A candidate fails the master exam for the second time. Under 22 TAC §363.22, the next attempt may be taken after waiting at least:

  • a.60 days✓
  • b.180 days
  • c.7 days
  • d.365 days

The waiting period is 30 days after the first failure, 60 days after the second and 90 days after the third and later failures. The pass mark is 70 percent.22 TAC §363.22

Plumbing License Law and Board Rules

A master plumber licensed in another state applies in Texas. Under §1301.3581, the Board may waive a prerequisite where the other jurisdiction's requirements are:

  • a.Published in a national trade magazine
  • b.Less strict than the requirements of Texas
  • c.Substantially equivalent to those of Texas✓
  • d.Approved by the applicant's former employer

The Board may waive prerequisites for an applicant holding a similar license from a jurisdiction with substantially equivalent requirements; formal reciprocity agreements need the governor's approval.Tex. Occ. Code §1301.3581

Plumbing License Law and Board Rules

Under §1301.303, how often must the Board update the complainant and the subject of a complaint on the status of an investigation?

  • a.Once, when the complaint is first received
  • b.At least quarterly, until final disposition✓
  • c.Never, because investigations are confidential
  • d.At least daily, until final disposition

The Board notifies the complainant and each subject of the complaint of the status at least quarterly until final disposition, unless notice would jeopardise an undercover investigation.Tex. Occ. Code §1301.303

Plumbing License Law and Board Rules

A master plumber installs a multipurpose residential fire protection sprinkler system. Under 22 TAC §367.8, the system must be installed to:

  • a.NFPA 54, by any plumber with a medical gas endorsement
  • b.NFPA 99, by a registered residential utilities installer
  • c.NFPA 13D, by a holder of the sprinkler specialist endorsement✓
  • d.NFPA 58, by a drain cleaner registered with the Board

Multipurpose residential sprinkler systems share piping with the domestic water system and are installed to NFPA 13D by a master or journeyman holding the Multipurpose Residential Fire Protection Sprinkler Specialist endorsement.22 TAC §367.8; Tex. Occ. Code §1301.3565

Plumbing Mathematics

A 45-degree offset must move a pipe 20 inches sideways. Using the constant 1.414, the centre-to-centre travel between the two 45-degree fittings is about:

  • a.40.0 inches
  • b.28.3 inches✓
  • c.20.0 inches
  • d.14.1 inches

Travel for a 45-degree offset equals the offset times 1.414: 20 × 1.414 = 28.28 inches. Dividing by 1.414 gives 14.1, which is the mistake of running the formula backwards.

Plumbing Mathematics

A 60-degree offset (using 60-degree bends measured from the pipe run) has an offset of 30 inches. Using the constant 1.155, the travel is about:

  • a.42.4 inches
  • b.60.0 inches
  • c.26.0 inches
  • d.34.7 inches✓

Travel for a 60-degree offset equals offset × 1.155 = 34.65 inches. The constant 1.414 belongs to 45-degree fittings and would give 42.4.

Plumbing Mathematics

A 22-1/2-degree offset must move a pipe 10 inches. Using the constant 2.613, the travel is about:

  • a.26.1 inches✓
  • b.11.5 inches
  • c.38.3 inches
  • d.14.1 inches

Travel for a 22-1/2-degree offset equals offset × 2.613 = 26.13 inches. Shallow fittings need a long travel to gain a small offset.

Plumbing Mathematics

A 4-inch building drain runs 120 feet at a slope of 1/8 inch per foot. The total fall is:

  • a.30 inches
  • b.15 inches✓
  • c.9.6 inches
  • d.96 inches

Fall equals length times slope: 120 × 1/8 = 15 inches. Thirty inches would be the fall at 1/4 inch per foot.

Plumbing Mathematics

A building sewer must drop 2 feet 6 inches over a run of 120 feet. The slope is:

  • a.1/2 inch per foot
  • b.1/4 inch per foot✓
  • c.1/8 inch per foot
  • d.1/16 inch per foot

Two feet 6 inches is 30 inches; 30 ÷ 120 = 0.25 inch per foot. At 1/8 inch per foot the same run would drop only 15 inches.

Plumbing Mathematics

A slope of 1/4 inch per foot is equal to a grade of about:

  • a.0.25 percent
  • b.4.0 percent
  • c.25 percent
  • d.2.1 percent✓

One quarter inch in 12 inches is 0.25 ÷ 12 = 0.0208, or about 2.1 percent. Treating 1/4 inch as 25 percent ignores the 12-inch run.

Plumbing Mathematics

What pressure does a column of water 100 feet high exert at its base? (Use 0.433 psi per foot.)

  • a.62.4 psi
  • b.43.3 psi✓
  • c.23.1 psi
  • d.231 psi

Pressure equals height × 0.433: 100 × 0.433 = 43.3 psi. The figure 2.31 is the inverse constant, feet of head per psi.

Plumbing Mathematics

A booster pump must deliver 20 psi at a fixture 80 feet above the pump. Ignoring friction, the pump discharge pressure must be about:

  • a.20.0 psi
  • b.100 psi
  • c.34.6 psi
  • d.54.6 psi✓

Static loss is 80 × 0.433 = 34.6 psi, and 20 psi must remain at the fixture: 34.6 + 20 = 54.6 psi. Friction loss would be added to that in a real design.

Plumbing Mathematics

A gauge at the base of a water riser reads 65 psi with no flow. How high can that pressure lift water? (Use 2.31 feet per psi.)

  • a.About 28 feet
  • b.About 65 feet
  • c.About 300 feet
  • d.About 150 feet✓

Head equals pressure × 2.31: 65 × 2.31 = 150 feet. Dividing instead of multiplying gives 28, which is the usual error.

Plumbing Mathematics

A rectangular tank is 6 feet long, 4 feet wide and 3 feet deep. How many gallons does it hold? (7.48 gallons per cubic foot.)

  • a.About 539 gallons✓
  • b.About 600 gallons
  • c.About 231 gallons
  • d.About 72 gallons

Volume is 6 × 4 × 3 = 72 cubic feet, and 72 × 7.48 = 538.6 gallons. Seventy-two is the volume in cubic feet, not gallons.

Plumbing Mathematics

The water in a full 539-gallon tank weighs about how much? (8.33 pounds per gallon.)

  • a.2,245 pounds
  • b.539 pounds
  • c.4,490 pounds✓
  • d.33,600 pounds

Weight equals gallons × 8.33: 539 × 8.33 = 4,490 pounds. The structure carrying a tank has to support the water as well as the tank.

Plumbing Mathematics

A vertical cylindrical tank is 4 feet in diameter and 6 feet high. Its capacity is about: (Use 3.14 and 7.48.)

  • a.564 gallons✓
  • b.75 gallons
  • c.2,255 gallons
  • d.141 gallons

Area is 3.14 × 2 × 2 = 12.56 square feet; volume is 12.56 × 6 = 75.4 cubic feet; 75.4 × 7.48 = 564 gallons. Using the diameter in place of the radius gives four times too much.

Plumbing Mathematics

How many gallons does 100 feet of 4-inch pipe hold? (Gallons per foot = 0.0408 × diameter in inches squared.)

  • a.About 16 gallons
  • b.About 408 gallons
  • c.About 65 gallons✓
  • d.About 33 gallons

Gallons per foot = 0.0408 × 4 × 4 = 0.653; over 100 feet that is 65.3 gallons. Forgetting to square the diameter gives 16.

Plumbing Mathematics

A water test fills 100 feet of 4-inch stack. About how much does the water in the stack weigh? (65.3 gallons; 8.33 pounds per gallon.)

  • a.65 pounds
  • b.1,088 pounds
  • c.272 pounds
  • d.544 pounds✓

65.3 × 8.33 = 544 pounds. This is why stacks are supported at their base and at each floor before a water test.

Plumbing Mathematics

The cross-sectional area of a 4-inch pipe is how many times the area of a 2-inch pipe?

  • a.16 times
  • b.4 times✓
  • c.8 times
  • d.2 times

Area varies with the square of the diameter: (4 ÷ 2)² = 4. Doubling the diameter does not just double the area.