250 questions

Plumbing Mathematics

What is the internal cross-sectional area of a pipe with a 6-inch inside diameter? (Use 0.7854 × d².)

  • a.113 square inches
  • b.18.8 square inches
  • c.28.3 square inches✓
  • d.36.0 square inches

Area = 0.7854 × 6 × 6 = 28.27 square inches. The figure 18.8 is the circumference, and 113 comes from using the diameter as the radius.

Plumbing Mathematics

How many Btu are needed to heat 50 gallons of water from 60°F to 140°F? (8.33 pounds per gallon.)

  • a.About 58,300 Btu
  • b.About 4,000 Btu
  • c.About 33,300 Btu✓
  • d.About 16,700 Btu

Btu = gallons × 8.33 × temperature rise = 50 × 8.33 × 80 = 33,320. One Btu raises one pound of water one degree Fahrenheit.

Plumbing Mathematics

A gas water heater has an input of 40,000 Btu/h and is 80 percent efficient. About how many gallons per hour can it raise by 80°F?

  • a.96 gallons per hour
  • b.60 gallons per hour
  • c.24 gallons per hour
  • d.48 gallons per hour✓

Output is 40,000 × 0.80 = 32,000 Btu/h. Each gallon needs 8.33 × 80 = 666 Btu, so 32,000 ÷ 666 = 48 gallons per hour.

Plumbing Mathematics

A 4,500-watt electric element delivers about how many Btu per hour? (1 watt = 3.412 Btu/h.)

  • a.45,000 Btu/h
  • b.15,350 Btu/h✓
  • c.1,320 Btu/h
  • d.4,500 Btu/h

4,500 × 3.412 = 15,354 Btu/h. Dividing by 3.412 instead of multiplying gives 1,320.

Plumbing Mathematics

A 4,500-watt element operates on 240 volts. The current it draws is about:

  • a.53.33 amperes
  • b.9.4 amperes
  • c.37.5 amperes
  • d.18.75 amperes✓

Amperes = watts ÷ volts = 4,500 ÷ 240 = 18.75. The same element on 120 volts would not draw 37.5 amperes at full output, because its output would fall.

Plumbing Mathematics

Three gas appliances are rated 40,000, 100,000 and 65,000 Btu/h. With natural gas at 1,000 Btu per cubic foot, the total connected demand is:

  • a.100 cubic feet per hour
  • b.20.5 cubic feet per hour
  • c.2,050 cubic feet per hour
  • d.205 cubic feet per hour✓

Total input is 205,000 Btu/h; 205,000 ÷ 1,000 = 205 cubic feet per hour. Sizing only for the largest appliance, 100 cfh, undersizes the main.

Plumbing Mathematics

The same 205,000 Btu/h load is supplied with propane at about 2,500 Btu per cubic foot. The demand is:

  • a.820 cubic feet per hour
  • b.82 cubic feet per hour✓
  • c.512 cubic feet per hour
  • d.205 cubic feet per hour

205,000 ÷ 2,500 = 82 cubic feet per hour. Propane carries about two and a half times the heat of natural gas per cubic foot, so the volume is smaller.

Plumbing Mathematics

Mixing 30 gallons of water at 140°F with 20 gallons at 60°F gives a mixed temperature of:

  • a.92°F
  • b.108°F✓
  • c.100°F
  • d.120°F

Mixed temperature = (30 × 140 + 20 × 60) ÷ 50 = (4,200 + 1,200) ÷ 50 = 108°F. A simple average, 100°F, ignores the unequal volumes.

Plumbing Mathematics

A flat roof measures 100 feet by 80 feet, and the design rainfall rate is 4 inches per hour. The flow to be drained is about: (gpm = area × rate × 0.0104.)

  • a.3,200 gpm
  • b.333 gpm✓
  • c.167 gpm
  • d.83 gpm

8,000 square feet × 4 × 0.0104 = 332.8 gpm. Leaving out the rainfall rate gives 83 gpm, the flow for 1 inch per hour.

Plumbing Mathematics

One inch of rain falls on a 2,000-square-foot roof. About how many gallons run off? (7.48 gallons per cubic foot.)

  • a.624 gallons
  • b.14,960 gallons
  • c.167 gallons
  • d.1,247 gallons✓

One inch is 1/12 foot: 2,000 ÷ 12 = 166.7 cubic feet; 166.7 × 7.48 = 1,247 gallons. The figure 167 is the volume in cubic feet.

Plumbing Mathematics

A bathroom group has one water closet (3 dfu), one lavatory (1 dfu) and one bathtub (2 dfu). A branch serving four such groups carries:

  • a.24 dfu✓
  • b.12 dfu
  • c.48 dfu
  • d.6 dfu

Each group is 3 + 1 + 2 = 6 drainage fixture units, and four groups make 24. Fixture unit totals, not fixture counts, are taken to the sizing table.

Plumbing Mathematics

A sump pump discharges 30 gpm continuously into a drainage system. If each gpm of continuous flow counts as 2 drainage fixture units, the load is:

  • a.15 dfu
  • b.120 dfu
  • c.60 dfu✓
  • d.30 dfu

30 gpm × 2 = 60 drainage fixture units. The conversion lets pumped flows be added to gravity fixture loads on the same table.IPC §709.3

Plumbing Mathematics

A 3/4-inch pipe is cut for a run that measures 48 inches centre to centre between two 90-degree elbows. Each elbow has a fitting allowance (centre to face less thread engagement) of 7/8 inch. The cut length is:

  • a.49-3/4 inches
  • b.48 inches
  • c.46-1/4 inches✓
  • d.47-1/8 inches

Cut length equals centre-to-centre minus the allowance for both fittings: 48 − (2 × 7/8) = 46-1/4 inches. Subtracting for one fitting only gives 47-1/8.

Plumbing Mathematics

A job needs 1,250 feet of pipe, and the estimator adds 8 percent for waste. The quantity to order is:

  • a.2,250 feet
  • b.1,258 feet
  • c.1,350 feet✓
  • d.1,150 feet

1,250 × 1.08 = 1,350 feet. Adding 8 feet instead of 8 percent gives 1,258.

Plumbing Mathematics

Material for a job costs $4,000 and labour costs $6,000. With 15 percent added for overhead and then 10 percent profit on the subtotal, the price is:

  • a.$15,000
  • b.$11,500
  • c.$12,650✓
  • d.$12,500

Cost is $10,000; with overhead 10,000 × 1.15 = 11,500; with profit 11,500 × 1.10 = $12,650. Adding 25 percent in one step gives 12,500, which misses the compounding.

Plumbing Mathematics

A trench is 150 feet long, 2 feet wide and 4 feet deep. How many cubic yards are excavated?

  • a.About 44 cubic yards✓
  • b.About 1,200 cubic yards
  • c.About 133 cubic yards
  • d.About 400 cubic yards

Volume is 150 × 2 × 4 = 1,200 cubic feet; 1,200 ÷ 27 = 44.4 cubic yards. Dividing by 9 or by 3 confuses cubic yards with square or linear yards.

Plumbing Mathematics

Water flows at 20 gpm through a pipe. How many cubic feet pass in one hour? (7.48 gallons per cubic foot.)

  • a.About 160 cubic feet✓
  • b.About 1,200 cubic feet
  • c.About 8,976 cubic feet
  • d.About 2.7 cubic feet

20 gpm × 60 = 1,200 gallons per hour; 1,200 ÷ 7.48 = 160 cubic feet. The figure 1,200 is gallons, and multiplying by 7.48 gives 8,976.

Plumbing Mathematics

A rolling offset has a rise of 12 inches and a roll (spread) of 16 inches. The true offset is:

  • a.20 inches✓
  • b.14 inches
  • c.40 inches
  • d.28 inches

True offset is the square root of rise squared plus roll squared: √(144 + 256) = √400 = 20 inches. Adding the two sides gives 28, which is not the diagonal.

Plumbing Mathematics

Using the 20-inch true offset above with 45-degree fittings, the travel is about:

  • a.28.3 inches✓
  • b.52.3 inches
  • c.23.1 inches
  • d.20.0 inches

Travel = true offset × 1.414 = 20 × 1.414 = 28.3 inches. The constant 1.155 (23.1 inches) applies to 60-degree fittings.

Plumbing Mathematics

A pipe 200 feet long carries hot water, and the copper expands 1.1 inches per 100 feet for each 100°F of temperature rise. For an 80°F rise, the expansion is about:

  • a.1.76 inches✓
  • b.2.20 inches
  • c.0.88 inch
  • d.17.6 inches

Expansion = 1.1 × (200 ÷ 100) × (80 ÷ 100) = 1.76 inches. Ignoring the second hundred feet gives 0.88, and ignoring the temperature ratio gives 2.2.

Plumbing Codes: Design and Commercial Systems

A restaurant has an occupant load of 300. Under IPC §403.1.1, the fixture count is worked out by assuming the occupants are:

  • a.40 percent male and 60 percent female
  • b.100 percent of each sex, counted twice
  • c.60 percent male and 40 percent female
  • d.50 percent male and 50 percent female✓

Unless statistical data approved by the code official shows otherwise, the occupant load is divided half and half before the fixture ratios in Table 403.1 are applied to each sex.IPC §403.1.1

Plumbing Codes: Design and Commercial Systems

Under IPC §403.2, separate toilet facilities for each sex are NOT required in a structure or tenant space with a total occupant load, including employees and customers, of:

  • a.50 or fewer
  • b.75 or fewer
  • c.150 or fewer
  • d.15 or fewer✓

Separate facilities are not required for dwelling units and sleeping units, for spaces with a total occupant load of 15 or fewer, or for mercantile occupancies of 100 or fewer. Larger spaces need facilities for each sex.IPC §403.2

Plumbing Codes: Design and Commercial Systems

In a covered mall, IPC §403.3.4 limits the path of travel from a tenant space to the required public toilet facilities to:

  • a.1,000 feet
  • b.100 feet
  • c.750 feet
  • d.300 feet✓

In covered and open mall buildings the travel distance, measured from the main entrance of any store or tenant space, may not exceed 300 feet. Other occupancies use 500 feet.IPC §403.3.4

Plumbing Codes: Design and Commercial Systems

Under IPC §410.4, where approved water dispensers are provided in an office building, they may substitute for:

  • a.Not more than 10 percent of the required drinking fountains
  • b.None, because substitution is not allowed in any occupancy
  • c.All of the required drinking fountains in every occupancy
  • d.Not more than 50 percent of the required drinking fountains✓

Restaurants that provide drinking water free of charge need no fountains, and in other occupancies water dispensers may replace up to 50 percent of the required fountains.IPC §410.4

Plumbing Codes: Design and Commercial Systems

Under IPC §606.2, a shutoff valve is required on the fixture supply to each plumbing fixture EXCEPT:

  • a.Lavatories in commercial and public buildings
  • b.Kitchen sinks in apartment buildings of any height or age
  • c.Bathtubs and showers in one- and two-family dwellings✓
  • d.Water closets in one- and two-family dwellings

Shutoff valves are required on the supply to each fixture other than bathtubs and showers in one- and two-family dwellings and in hotel guest rooms that have unit shutoffs.IPC §606.2

Plumbing Codes: Design and Commercial Systems

A water distribution system is being sized. The water supply fixture unit is best described as:

  • a.A measure of the probable demand a fixture places on the supply✓
  • b.The pressure, in psi, required at the outlet of a fixture
  • c.The volume, in gallons, a fixture uses in a single operation
  • d.The actual flow, in gallons per minute, of a fixture's faucet or valve

A water supply fixture unit expresses the probable hydraulic demand of a fixture, allowing for the chance that not all fixtures run at once. Totals are converted to gpm with a demand curve or table.IPC §202; IPC Appendix E

Plumbing Codes: Design and Commercial Systems

When sizing a water system by the IPC Appendix E method, the pressure available for friction loss is found by taking the minimum street pressure and subtracting:

  • a.Static head loss, the pressure needed at the highest fixture and meter and device losses✓
  • b.Only the friction loss in the water service between the main and the meter
  • c.The pressure rating stamped on the pipe that is used for the water service
  • d.Only the pressure needed at the fixture that is nearest the water meter

Available friction pressure equals the minimum supply pressure less the elevation loss, the required residual at the most demanding outlet and losses through meters, backflow preventers and other devices. What remains is spread over the developed length.IPC Appendix E

Plumbing Codes: Design and Commercial Systems

The developed length of the piping to the most remote fixture is 200 feet, and 20 psi is available for friction loss. The allowable friction loss per 100 feet is:

  • a.20 psi per 100 feet
  • b.40 psi per 100 feet
  • c.10 psi per 100 feet✓
  • d.4 psi per 100 feet

Loss per 100 feet = available pressure × 100 ÷ developed length = 20 × 100 ÷ 200 = 10 psi. Designers usually increase the length for fittings before dividing.IPC Appendix E

Plumbing Codes: Design and Commercial Systems

Under IPC §604.3, the minimum flow pressure required at a flushometer valve water closet (siphonic, other than blowout type) is generally higher than at a lavatory faucet because:

  • a.The valve must pass a high flow rate in a few seconds to flush the bowl✓
  • b.The supply pipe to a flushometer is smaller than a lavatory supply
  • c.The valve contains a vacuum breaker that must be kept shut by water pressure
  • d.The fixture is always installed on the top floor of a building

Flushometer valves need a high instantaneous flow, so the table of required capacities at fixture outlets lists higher flow pressures for them than for faucets. The vacuum breaker and location are not the reason.IPC §604.3

Plumbing Codes: Design and Commercial Systems

Under IPC §607.2, the developed length of hot water piping from the source of hot water to a fixture may not exceed:

  • a.300 feet
  • b.10 feet
  • c.50 feet✓
  • d.150 feet

The maximum developed length from the source (a heater, a recirculating loop or heat-traced pipe) to the fixture is 50 feet, which limits the water wasted while waiting for hot water.IPC §607.2

Plumbing Codes: Design and Commercial Systems

Under IPC §501.2, a water heater that supplies both potable hot water and space heating at temperatures above 140°F must have:

  • a.A reduced pressure backflow assembly on its outlet
  • b.A master thermostatic mixing valve conforming to ASSE 1017✓
  • c.A pressure-reducing valve set to 25 psi on its inlet
  • d.A second relief valve conforming to ASME Section VIII

Where a combination system heats water above 140°F for space heating, a tempering valve complying with ASSE 1017 limits the water sent to the potable distribution system to 140°F or less.IPC §501.2

Plumbing Codes: Design and Commercial Systems

"Tempered water" for public hand-washing facilities is defined in the IPC as water between:

  • a.60°F and 80°F
  • b.110°F and 140°F
  • c.85°F and 110°F✓
  • d.140°F and 180°F

Tempered water has a temperature range of 85°F to 110°F and is delivered to public hand-washing fixtures through an approved temperature-limiting device.IPC §§202, 607.1.2

Plumbing Codes: Design and Commercial Systems

Under IPC §604.9, a water hammer arrestor installed where quick-closing valves are used must conform to:

  • a.ASSE 1013
  • b.ASSE 1070
  • c.ASSE 1016
  • d.ASSE 1010✓

Water hammer arrestors conform to ASSE 1010 and are installed per the manufacturer's instructions. ASSE 1016 covers shower valves, 1070 temperature limiters and 1013 reduced pressure assemblies.IPC §604.9

Plumbing Codes: Design and Commercial Systems

A commercial building's fire sprinkler system has an antifreeze loop. Under IPC §608.16.4.1, the potable supply must be protected by:

  • a.A double check valve assembly without test cocks
  • b.A reduced pressure principle backflow prevention assembly✓
  • c.A single swing check valve on the fire service
  • d.An atmospheric vacuum breaker above the riser

Where a fire protection system contains chemical additives or antifreeze, a reduced pressure principle assembly is required. A double check assembly is accepted only where no additives are used.IPC §608.16.4.1

Plumbing Codes: Design and Commercial Systems

Under IPC §608.17.4, the potable water supply to an automatic sprinkler system that has a fire department connection must be protected by at least:

  • a.A double check backflow prevention assembly✓
  • b.An air gap at the fire department connection
  • c.No protection, since the water is potable
  • d.A hose connection vacuum breaker on the riser

The potable supply to automatic sprinkler and standpipe systems is protected by a double check backflow prevention assembly, a double check fire protection backflow prevention assembly or a reduced pressure principle fire protection backflow prevention assembly. Only systems installed as part of the water distribution system with no fire department connection are exempt.IPC §608.17.4

Plumbing Codes: Design and Commercial Systems

A carbonated beverage dispenser is connected to the water supply. Under IPC §608.16.1, the supply is protected by a backflow preventer conforming to ASSE 1022 or an air gap, and the piping downstream of the device may not be:

  • a.Stainless steel
  • b.Polyethylene tubing
  • c.Copper✓
  • d.Braided food-grade hose

Carbonated water is acidic and leaches copper, so the piping from the backflow preventer to the carbonator is not affected by carbon dioxide; copper is excluded. Stainless steel and listed plastics are used.IPC §608.16.1

Plumbing Codes: Design and Commercial Systems

Under IPC §608.8, non-potable water piping in a building with a dual water system must be identified:

  • a.By a note on the drawings only, because field marking fades with time
  • b.By painting the pipe hangers yellow wherever the pipe is exposed to view in a mechanical room or shaft
  • c.By colour marking, metal tags or tape at intervals of 25 feet or less and at each floor or wall penetration✓
  • d.By a single label at the water meter that lists every non-potable outlet in the building by room number

Where non-potable systems are installed, the piping is identified by colour marking or tags at intervals not exceeding 25 feet and at each point where it passes through a wall, floor or roof. Reclaimed water piping is purple.IPC §608.8

Plumbing Codes: Design and Commercial Systems

A drainage stack is 3 inches in diameter. Under IPC §710.1, the size of a stack is based on:

  • a.The total drainage fixture units connected and the stack height in branch intervals✓
  • b.The total developed length of all horizontal branches that connect to it
  • c.The diameter of the building sewer at the point where it leaves the lot
  • d.The number of water closets connected, whatever the other fixtures may be

Stack size comes from the table of horizontal fixture branches and stacks, entered with the total fixture units, the load per branch interval and whether the stack is more than three branch intervals high.IPC §710.1

Plumbing Codes: Design and Commercial Systems

A "branch interval", as used for sizing stacks in the IPC, is a vertical length of stack of at least:

  • a.2 feet, within which the horizontal branches from one floor connect
  • b.8 feet, within which the horizontal branches from one floor connect✓
  • c.20 feet, within which the branches from two floors connect
  • d.40 feet, within which the branches from four floors connect

A branch interval is a vertical measurement of distance, 8 feet or more in developed length, between the connections of horizontal branches to a stack; it usually corresponds to a story.IPC §202

Plumbing Codes: Design and Commercial Systems

Under IPC §711.1, a horizontal branch may not connect to the building drain or a horizontal offset within what distance downstream of a stack?

  • a.50 times the diameter of the drainage stack
  • b.10 times the diameter of the drainage stack✓
  • c.100 times the diameter of the drainage stack
  • d.2 times the diameter of the drainage stack

Hydraulic jump at the base of a stack creates pressure, so horizontal branches connect at least 10 stack diameters downstream of the stack. Closer connections risk blown trap seals.IPC §711.1

Plumbing Codes: Design and Commercial Systems

Under IPC §904.2, a vent stack is required for a drainage stack that has:

  • a.Twenty or more branch intervals
  • b.Five or more branch intervals✓
  • c.Two or more branch intervals
  • d.Ten or more branch intervals

A vent stack is required for every drainage stack of five branch intervals or more, except stacks designed as waste stack vents or served by other approved systems.IPC §904.2

Plumbing Codes: Design and Commercial Systems

Under IPC §908.1, a soil or waste stack in a building of more than 10 branch intervals needs a relief vent at:

  • a.Each second interval, counting from the lowest floor
  • b.The top interval only, just below the roof
  • c.The lowest interval only, just above the base
  • d.Each tenth interval, counting from the top floor✓

Stacks of more than 10 branch intervals have a relief vent at each tenth interval installed, beginning with the top floor, to equalise pressure between the drainage stack and the vent stack.IPC §908.1

Plumbing Codes: Design and Commercial Systems

Under IPC §904.4, a vent stack must connect to the drainage stack:

  • a.At or below the lowest horizontal branch✓
  • b.At the midpoint of the drainage stack
  • c.At the roof, through the vent terminal
  • d.Above the highest horizontal branch only

Every vent stack connects to the base of the drainage stack, at or below the lowest horizontal branch, or to the building drain within 10 stack diameters downstream, so that pressure at the base is relieved.IPC §904.4

Plumbing Codes: Design and Commercial Systems

A sewage ejector sump is vented. Under IPC §906.5.1, the sump vent for a sewage pump or ejector other than a pneumatic ejector may not be smaller than:

  • a.3/4 inch
  • b.4 inches
  • c.1-1/4 inches✓
  • d.2-1/2 inches

Sump vents are sized by the pump discharge rate and vent length, with a minimum of 1-1/4 inches. Pneumatic ejectors need a separate relief vent of at least 1-1/4 inches run independently to outdoors.IPC §906.5

Plumbing Codes: Design and Commercial Systems

Under IPC §712.3.5, the discharge pipe from a sewage ejector must connect to the gravity drain through:

  • a.A saddle fitting, strapped over a hole cut in the drain
  • b.A double sanitary tee shared with a nearby fixture drain
  • c.A sanitary tee, entering on its side at the centreline of the pipe
  • d.A wye fitting, entering from the top of the horizontal drain✓

Pumped discharge enters a horizontal drain from the top through a wye, at least 10 pipe diameters from the base of any stack, so the pumped flow does not back up into gravity branches.IPC §712.3.5

Plumbing Codes: Design and Commercial Systems

Under IPC §712.4.2, a sewage ejector that receives the discharge of water closets must be able to pass solids of at least:

  • a.2 inches in diameter, unless it is a grinder pump✓
  • b.6 inches in diameter, in every installation
  • c.4 inches in diameter, unless it is a grinder pump
  • d.1/4 inch in diameter, in every installation

Sewage pumps and ejectors receiving water closet waste handle spherical solids up to 2 inches and have a discharge of at least 2 inches; grinder pumps and grinder ejectors may use a 1-1/4-inch discharge.IPC §712.4.2

Plumbing Codes: Design and Commercial Systems

A building has fixtures on a floor below the level of the public sewer. Under IPC §712.1, the waste from those fixtures must:

  • a.Flow to a dry well under the floor slab of the lowest level
  • b.Discharge to a tightly covered, vented sump and be pumped to the gravity drain✓
  • c.Flow by gravity through a backwater valve into the public sewer
  • d.Discharge to an open floor sump that is emptied by hand each week

Building subdrains that cannot discharge by gravity go to a sealed and vented sump, from which the contents are lifted by an automatic pump or ejector. A backwater valve cannot make water run uphill.IPC §712.1

Plumbing Codes: Design and Commercial Systems

Storm drainage for a roof is sized, under IPC §1106.1, on the basis of:

  • a.The 2-year, 24-hour rainfall total for the location
  • b.The heaviest rainfall of the previous year
  • c.The average annual rainfall for the county
  • d.The 100-year, 1-hour rainfall rate for the location✓

Vertical conductors, leaders, building storm drains and sewers are sized for the 100-year hourly rainfall rate, taken from the code's maps or approved local weather data.IPC §1106.1

Plumbing Codes: Design and Commercial Systems

A storm water sump pit is installed for a building subdrain. Under IPC §1113.1.2, the pit must be at least:

  • a.60 inches in diameter and 96 inches deep
  • b.36 inches in diameter and 72 inches deep
  • c.6 inches in diameter and 12 inches deep
  • d.18 inches in diameter and 24 inches deep✓

A storm sump pit is not less than 18 inches in diameter and 24 inches deep, accessible, with a removable cover that can carry the expected loads. A smaller pit short-cycles the pump.IPC §1113.1.2

Plumbing Codes: Design and Commercial Systems

Where a parapet would trap water if the primary roof drains were blocked, IPC §1108.1 requires:

  • a.A larger vent stack through the roof
  • b.A sump pump installed on the roof surface
  • c.Secondary (emergency) roof drains or scuppers✓
  • d.A second layer of roofing membrane over the deck

Where roof perimeter construction extends above the roof so that water would be entrapped if the primary drains allowed build-up, secondary drains or scuppers are required.IPC §1108.1