A specialty (Class C) contractor takes a prime contract. The license law permits a specialty contractor to take a prime contract when?

a.Never
b.Only for projects over $1 million
c.Only with a Class A partner
d.When the project is within the contractor's specialty and any incidental work is related to that specialty

Explicación

Under B&P Code section 7059, a specialty contractor may take a prime contract for a project within its trade. Any additional trades must be incidental and supplemental to that specialty, or properly subcontracted.

Referencia Legal: B&P Code §7059