Contratos y EjecuciónPregunta 751 de 1605

A contractor prepares a home improvement contract but leaves the completion date blank, intending to 'figure it out later.' This contract:

a.Violates §7159, which requires approximate start and completion dates to be stated
b.Only needs a start date
c.Is fully compliant
d.Is fine because dates are estimates

Explicación

B&P §7159 requires the contract to state the approximate start and completion dates. Leaving the completion date blank is a violation and reflects a prohibited blank-space practice.

Referencia Legal: B&P §7159

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar