Contratos y EjecuciónPregunta 753 de 1605
The $500 threshold that triggers a written home improvement contract is measured by:
a.The aggregate contract price, including both labor and materials
b.Labor cost only
c.The permit fee
d.Materials cost only
Explicación
B&P §7159 uses the aggregate contract price, combining labor and materials, to determine whether the $500 threshold requiring a written contract is exceeded.
Referencia Legal: B&P §7159Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Under a service and repair contract, the total price includes:
- A contractor prepares a home improvement contract but leaves the completion date blank, intending to 'figure it out later.' This contract:
- What must a home improvement contract state about extra or unforeseen work discovered mid-project?
- A home improvement salesperson may lawfully:
- Which is TRUE about a home improvement contract that omits the required Mechanics Lien Warning?
- The five-business-day cancellation right is extended to which category of home improvement buyers?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)