Contratos y EjecuciónPregunta 757 de 1605

A homeowner insists on paying the full $30,000 up front to 'lock in the price.' The contractor should know that accepting this:

a.Is required to reserve materials
b.Is required if the owner offers
c.Would violate the down payment limit and payment-for-work-performed rules absent a joint control
d.Is fine because the owner volunteered

Explicación

Even if the owner offers, B&P §7159 prohibits accepting a down payment over $1,000 (or 10%) and payments exceeding the value of work performed, unless funds are held by an approved joint control.

Referencia Legal: B&P §7159(d)