Contratos y EjecuciónPregunta 758 de 1605
Which is a required feature of the progress payment schedule in a home improvement contract?
a.It may be left to the contractor's later discretion
b.Each payment amount must be stated and tied to a described phase of work
c.It may only be expressed as a single lump sum due at start
d.It must be paid entirely at signing
Explicación
B&P §7159 requires the schedule of progress payments to state each payment's dollar amount and correlate it to a specifically described phase of the work.
Referencia Legal: B&P §7159Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Which is TRUE about a home improvement contract that omits the required Mechanics Lien Warning?
- The five-business-day cancellation right is extended to which category of home improvement buyers?
- A homeowner insists on paying the full $30,000 up front to 'lock in the price.' The contractor should know that accepting this:
- A contractor performing a $700 service and repair job collects a $150 deposit before starting. This is:
- Which best describes when the contract price and payment terms must be filled in on a home improvement contract?
- The 'Three-Day Right to Cancel' notice given to a home improvement buyer must include:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)