Contratos y EjecuciónPregunta 768 de 1605
Which is a required condition for a service and repair contract under §7159.10?
a.The job must exceed $1,000
b.The contractor must offer a payment plan
c.The transaction is initiated by the buyer, not solicited door-to-door by the contractor
d.The buyer must be over 65
Explicación
B&P §7159.10 requires that the buyer initiated the contact requesting the service, distinguishing it from door-to-door solicitation, and caps the price at $750.
Referencia Legal: B&P §7159.10Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- The down payment limit of $1,000 or 10% (whichever is less) applies to:
- A homeowner signs a contract that does not include the contractor's license number. This omission:
- The primary purpose of requiring detailed written home improvement contracts is to:
- A contractor uses one contract to cover both a $400 gutter cleaning and a $9,000 addition, calling the whole thing a 'service call.' The addition portion:
- When a contract funds are placed in an approved joint control, the joint control company's role is to:
- A home improvement contract must be dated. The date is important primarily because it:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)