Contratos y EjecuciónPregunta 770 de 1605
When a contract funds are placed in an approved joint control, the joint control company's role is to:
a.Disburse funds to the contractor as work is verified complete
b.Perform the construction work
c.Sell the property
d.Issue the building permit
Explicación
A joint control (funding control) company holds the project funds and releases them to the contractor only as work is verified, which is why standard payment limits may be relaxed when one is used.
Referencia Legal: B&P §7159Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- The primary purpose of requiring detailed written home improvement contracts is to:
- Which is a required condition for a service and repair contract under §7159.10?
- A contractor uses one contract to cover both a $400 gutter cleaning and a $9,000 addition, calling the whole thing a 'service call.' The addition portion:
- A home improvement contract must be dated. The date is important primarily because it:
- Abandoning a home improvement project without legal excuse after starting is:
- A contractor's home improvement contract lists the total price but no breakdown of the payment schedule. Under §7159, this is:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)