Contratos y EjecuciónPregunta 777 de 1605

The requirement that a home improvement contract be signed before work begins protects the buyer by:

a.Waiving the contractor's liability
b.Ensuring the terms and cancellation rights are set before the buyer is committed to ongoing work
c.Guaranteeing the lowest price
d.Eliminating the need for permits

Explicación

Requiring signature before work begins ensures the buyer knows the full terms and retains the right to cancel before becoming entangled in a partially completed project.

Referencia Legal: B&P §7159

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar