Services & DistributionPregunta 49 de 110

A legally required standby system must supply its loads within what maximum time after loss of normal power?

a.60 seconds
b.10 seconds
c.30 seconds
d.120 seconds

Explicación

Legally required standby systems must be able to supply their loads within 60 seconds of a normal-source failure.

Referencia Legal: 2023 NEC 701.12