A stop payment notice, unlike a mechanics lien, does NOT need to be:
a.Supported by a valid claim
b.Given by someone who furnished work
c.Served on the correct party
d.Recorded with the county recorder
Giải thích
A stop payment notice is served, not recorded; it directs the owner or lender to withhold funds. A mechanics lien, by contrast, is recorded against the property. Both require a valid underlying claim by someone who furnished work and proper service.
Trích dẫn luật: Civ. Code §8500Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
- A design professional (e.g., architect) who provided services for a private work of improvement authorized by the owner:
- An owner asks the contractor to provide a certificate of insurance naming the owner as additional insured. For the owner to actually have that status, the certificate must be accompanied by, or reflect:
- A contractor hires day laborers and pays them cash, believing they are 'independent contractors,' and carries no workers' compensation. If a laborer is injured, the contractor most likely:
- A supplier first delivered materials on Day 1 but did not serve its preliminary notice until Day 40. Under the notice rules, the supplier may claim a lien/stop-notice for materials furnished:
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)