A supplier first delivered materials on Day 1 but did not serve its preliminary notice until Day 40. Under the notice rules, the supplier may claim a lien/stop-notice for materials furnished:
a.Only for materials delivered after Day 60
b.For nothing at all
c.For the entire delivery history from Day 1
d.Within the 20 days before service (from about Day 20) and thereafter, but not for the earliest deliveries
Giải thích
Civil Code §8204 limits a late preliminary notice's reach to work furnished within 20 days before the notice was served, plus everything after. Deliveries made more than 20 days before service (the earliest ones) fall outside the protected window.
Trích dẫn luật: Civ. Code §8204Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- An owner asks the contractor to provide a certificate of insurance naming the owner as additional insured. For the owner to actually have that status, the certificate must be accompanied by, or reflect:
- A stop payment notice, unlike a mechanics lien, does NOT need to be:
- A contractor hires day laborers and pays them cash, believing they are 'independent contractors,' and carries no workers' compensation. If a laborer is injured, the contractor most likely:
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)